Belgian authorities ordered Google to halt construction of a major data center near Charleroi on Friday, citing the illegal erection of a three-hectare building without a valid permit.
The Walloon regional administration issued the stop-work order after inspectors visited the 50-hectare former mining site spanning Farciennes, Sambreville, and Aiseau-Presles, where roughly 300 workers were active. “We have identified a major violation: the illegal construction of a building covering three hectares,” Nicolas Yernaux, spokesperson for the Walloon government, told AFP. An official report will be sent to the prosecutor’s office.
The intervention followed a Greenpeace alert supported by drone footage showing significant progress in November. “The tech giant is continuing its work even though the latest version of its permit was revoked last August,” the environmental group said. It warned that “the climate crisis in our region will only intensify. In this scenario, the construction of energy-intensive giants cannot go unnoticed.”

Google has appealed the Walloon region’s refusal of its permit amendment to the administrative court, with a hearing scheduled for early January, according to regional authorities. The tech giant had requested changes to its 2024 permit to expand the building’s footprint and install a water-cooling system drawing from the Sambre River.
The regional government confirmed an official report will be transmitted to the prosecutor’s office, as Nicolas Yernaux, spokesperson for the Walloon administration, noted an infraction had been observed, according to Swissinfo. Greenpeace had initiated an urgent procedure after drone footage showed the site was actively progressing in November despite the permit’s revocation.
The “Stop Data Center” collective had mobilized against the project, arguing that the prolonged drought required preserving the Sambre River’s water. Regional Infrastructure Minister François Desquesnes rejected Google’s permit modification this summer amid citizen mobilization and environmental concerns.
The dispute centers on a permit modification Google requested this year to switch from air-cooling to a system drawing water from the Sambre River, according to Ilsole24Ore. Regional Infrastructure Minister François Desquesnes rejected the amendment this summer amid a prolonged drought and opposition from the “Stop Data Center” collective, which argued the river’s water must be preserved. Google appealed the refusal, with a hearing scheduled for January.
Yernaux stated work could have continued under the original 2024 permit, but the company built the new structure as if the modified permit had been granted. “They built the new building as if they had obtained it, but they did not have it,” he told AFP.
Google did not immediately respond to requests for comment. The case adds to regulatory hurdles for the company’s AI infrastructure push; Finnish police opened a criminal investigation into environmental impacts at a planned site in Muhos last month.