Belgian Authorities Order Google to Halt Data Centre Construction Near Charleroi

Belgian authorities ordered Google to suspend construction on a three-hectare data centre building near Charleroi after finding work continued without a valid permit.

Inspectors Stop Unpermitted Work

Inspectors visited the site at a former mining location straddling Farciennes, Sambreville, and Aiseau-Presles. Raphaël Stokis said structural work on the large building was nearly finished despite the planning permission being refused.

The regional official told the public broadcaster VRT that roughly 300 workers on the property were given a verbal stop order. This order was subsequently confirmed in writing to Google.

Google originally secured a permit in 2024 to construct three smaller, air-cooled data centres on the 50-hectare business park. In 2025, the company merged two of the facilities into a single large structure.

Google applied to switch to a liquid cooling system drawing 600 cubic metres of water an hour from the nearby River Sambre.

The Walloon administration initially approved the amendments in April. Regional infrastructure minister François Desquesnes revoked the modified permit in August following appeals from residents and protest groups over severe regional droughts.

Nicolas Yernaux, spokesperson for the Wallonia regional authorities, told Agence France-Presse that investigators identified a major offence involving the illegal construction of a three-hectare building. They prepared a report for public prosecutors.

“Ils ont construit le nouveau bâtiment comme s’ils l’avaient eu, or ils ne l’avaient pas (ce permis amendé),” said Nicolas Yernaux, spokesperson for the Wallonia regional authorities, according to Medias24.

Belgian Authorities Order
Photo: letemps.ch

Yernaux said that “They built the new building as if they had obtained the amended permit, but they had not,” as reported by Le Temps.

Greenpeace Protests Water Use

The enforcement action followed an emergency request by Greenpeace Belgium. The group used satellite imagery and drone footage to document ongoing construction at the site in November.

Joeri Thijs, spokesperson for Greenpeace Belgium, condemned the activity in comments reported by Data Center Dynamics.

“That Google continues to build without a permit is disrespectful to the environment, local residents, and the law,” said Joeri Thijs, spokesperson for Greenpeace Belgium.

The environmental organization said that Google’s existing data centre campus in Saint-Ghislain withdraws roughly one billion litres of water annually. The facility returns a quarter and evaporates the rest.

Greenpeace warned that the climate crisis will intensify in their region.

“The climate crisis will only intensify in our region. Against this backdrop, the construction of energy-guzzling behemoths cannot be allowed to go unnoticed,” Greenpeace Belgium said, as reported by The Korea Times.

Google challenged the August permit revocation by petitioning Belgium’s Council of State on October 17 to suspend and annul the decision.

Greenpeace reports construction halt at googles belgian data center
Photo: Unite.AI

Greenpeace and several local residents submitted requests to intervene in the proceedings on November 16. A public hearing is scheduled for January 7.

Legal Standards and Compliance Monitoring

“Tech giants are not above the law,” said Nadia Cornejo, a Greenpeace Belgium spokesperson, as reported by The Next Web.

Cornejo said this enforcement action should already have happened in August when authorities initially cancelled the planning permission. Following the intervention, Cornejo welcomed the reported stoppage and confirmed that Greenpeace would continue monitoring activity at the Aiseau-Presles site.

Google said in an official release that it remained committed to maintaining an open and collaborative dialogue with the regional authorities.

The Walloon administration confirmed to Agence France-Presse that it had formally issued an order of work stoppage due to the illegal construction that took place over recent weeks.

Broader European Context

The dispute in Wallonia unfolds as technology firms encounter regulatory scrutiny across Europe while expanding infrastructure to support artificial intelligence operations.

Finnish authorities ordered construction halted at two Google sites in October until mandatory environmental impact assessments were completed.

Photo of author

Economy Desk

Economy Desk at Archyde.

Stade Rochelais Confirms Saturday Top 14 Fixture Against USAP at Stade Marcel-Deflandre

PSG Monitor Abde Ezzalzouli Despite Luis Enrique Winter Transfer Stance