Construction Begins on Northeast Building at Albury Wodonga Regional Hospital

Albury Wodonga Regional Hospital Project Begins With New Building Construction


Construction Has Begun On the New Two-Storey Northeast Building, Marking A Significant Milestone In The $558 Million albury Wodonga regional Hospital Project. this Project Is Jointly Funded By The NSW, Victorian, And Australian Governments, Representing One Of The Largest Regional Health Infrastructure Undertakings Currently In Progress Across New South Wales and Victoria.

hansen Yuncken,An Albury-Based Building Contractor,Was Appointed In June To Commence The Early Works. The Northeast Building Is Scheduled For Completion In 2026.

The Purpose-Built Northeast Building Will Accommodate A Variety Of Health Services Currently Located Within And Near the Existing Allied Health Building. This Initial phase Is Crucial For Enabling The Construction Of The Future Seven-Storey Clinical Services Building.

A Link Bridge will Connect The Northeast Building Directly To The Existing Hospital, Providing Convenient Access To Essential Areas Such As Wards, The Main Entry, And Medical Imaging. The Design Incorporates provisions For Future Expansion, Ensuring Long-Term Adaptability.

“The Approval Of The Northeast Building Represents A Vital Step Forward In The Transformative $558 Million Albury Wodonga Regional Hospital Project,” Stated Bill Appleby, Chief Executive Officer Of Albury Wodonga Health. “Our Focus Is On Delivering Health Infrastructure That Is Fit For Purpose, Allowing Us To Enhance Capacity And Capability To Provide Care closer To Home.”

Appleby Further Explained That This initial Stage will Facilitate The Relocation Of Essential Services And Prepare The site for Major Construction, Which Is Anticipated To Begin In Mid-2026 And be Completed By Late 2028. Construction Will Be Phased To Minimize Disruption To Staff, Visitors, And The Broader Community.All Albury Hospital Services Will Remain Operational Throughout The Construction Period.

Artist's impression: Northeast Building, entrance from main hospital
Artist’s impression: Northeast Building, entrance from main hospital

Frequently Asked Questions

  • What Is The total Cost Of The Albury Wodonga Regional Hospital Project? The Project Is Valued At $558 million.
  • when Is The Northeast Building Expected To Be Completed? Construction Of The Northeast Building Is Scheduled For Completion In 2026.
  • Will Hospital Services Be Affected During Construction? All Albury Hospital Services Will Continue To Operate throughout The Construction Period.
  • Who Is The Contractor For The Early Works? Hansen Yuncken, An Albury-Based Building Contractor, Has Been Appointed To Deliver The Early Works.

Related Articles

Stay Informed: Share This Article With Your Network And Leave A Comment Below To Join The Conversation!

What potential impacts could the 36-month construction timeline have on existing hospital services and patient access?

Construction Begins on Northeast Building at Albury Wodonga Regional Hospital

Project Overview: Expanding Healthcare in the Border Region

Ground has officially broken on the highly anticipated Northeast Building at the Albury Wodonga Regional Hospital (AWRH). This notable infrastructure project represents a considerable investment in healthcare for the albury-Wodonga region, addressing growing community needs and modernizing medical facilities. The new building is a cornerstone of the hospital’s broader redevelopment plan, aiming to enhance patient care, improve operational efficiency, and attract top medical professionals. This expansion focuses on key service areas currently experiencing capacity constraints.

Key Features of the Northeast Building

The Northeast Building will deliver a range of crucial healthcare services.Here’s a breakdown of the planned facilities:

Expanded Emergency Department: A larger, more modern Emergency Department designed to handle increased patient volumes and provide faster, more effective emergency care. This includes dedicated bays for critical care, trauma, and paediatric emergencies.

Increased Intensive Care unit (ICU) Capacity: Additional ICU beds to meet the rising demand for critical care services, particularly during peak seasons and public health events.

Enhanced Surgical Suites: State-of-the-art surgical theatres equipped wiht the latest technology, supporting a wider range of surgical procedures and improved patient outcomes.

Dedicated Rehabilitation Services: A dedicated rehabilitation unit offering thorough physiotherapy, occupational therapy, and speech pathology services to aid patient recovery.

improved Maternity Services: Modernized maternity wards and birthing suites, providing a cozy and supportive habitat for expectant mothers and their families.

Integrated Medical Imaging: Advanced medical imaging facilities, including MRI, CT scanning, and X-ray, integrated with the new building for streamlined diagnostics.

Construction timeline & Stages

The construction project is expected to be completed in phases, with an estimated overall timeline of approximately 36 months.Key stages include:

  1. Site Preparation & Excavation (August – November 2025): This initial phase involves clearing the site, conducting necessary excavations, and establishing essential infrastructure.
  2. Foundation & Structural Work (November 2025 – June 2026): Focusing on laying the foundations and constructing the building’s structural framework.
  3. Building Enclosure & Fit-Out (June 2026 – December 2027): This stage encompasses the installation of the building’s exterior cladding, roofing, windows, and internal fit-out, including walls, flooring, and ceilings.
  4. Medical Equipment Installation & Commissioning (December 2027 – August 2028): The final phase involves installing and commissioning all medical equipment, conducting thorough testing, and preparing the building for operation.

Regular updates on the construction progress will be provided through the AWRH website and local media channels. Project management will prioritize minimizing disruption to existing hospital services during the construction period.

Impact on Hospital Services During Construction

The hospital is committed to maintaining the highest standards of patient care throughout the construction process. Strategies to mitigate disruption include:

phased Construction: Construction will be carried out in phases to minimize impact on specific departments.

Temporary Relocations: Some services might potentially be temporarily relocated to option areas within the hospital campus. Clear signage and communication will guide patients and visitors.

Noise Reduction Measures: Contractors will implement noise reduction measures to minimize disturbance to patients and staff.

Traffic Management Plan: A comprehensive traffic management plan will be in place to ensure safe access to the hospital for patients, visitors, and emergency vehicles.

Economic Benefits & Local Employment

The Northeast Building project is expected to generate significant economic benefits for the albury-Wodonga region.

Job Creation: The construction phase will create hundreds of direct and indirect jobs for local workers,including tradespeople,engineers,and project managers.

local Supplier Engagement: The hospital is committed to prioritizing the use of local suppliers and contractors whenever possible, boosting the regional economy.

Increased Healthcare Investment: The project demonstrates a strong commitment to healthcare investment in the region, attracting further economic development.

Skills Development: Opportunities for skills development and training will be provided to local workers involved in the project.

Albury-Wodonga Regional Hospital Redevelopment: A Broader Outlook

The Northeast Building is just one component of a larger, multi-stage redevelopment plan for the AWRH. Other key projects include:

refurbishment of Existing Wards: Upgrading and modernizing existing patient wards to improve comfort and functionality.

Expansion of Outpatient Services: Increasing capacity for outpatient clinics and specialist consultations.

Development of a New Central Sterile Services Department (CSSD): A state-of-the-art CSSD to ensure the highest standards of sterilization and infection control.

Infrastructure upgrades: Investing in essential infrastructure upgrades, including power, water, and IT systems.

Funding & Stakeholders

The Northeast Building project

You may also like

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Adblock Detected

Please support us by disabling your AdBlocker extension from your browsers for our website.