Nation confirmed what the authorization process will be like

2023-06-15 22:51:48

Through a brief statement, The national government confirmed what the authorization process will be like of the Néstor Kirchner gas pipeline that will begin, as plannedor, next Tuesday June 20. It will be filled in six stages, which will take almost 20 days, and The official inauguration will be on Sunday, July 9.

The Ministry of Economy, the Secretariat of Energy and Energy Argentina SA (ENARSA) announce that the proposed objective has been met and next Tuesday, June 20, the valve will open and the filling process of the President Néstor Kirchner Gas Pipeline will begin,” says the official government announcement.

They detailed that the gas pipeline filling process responds to “usual procedures” in this type of system, which involves phases of Sweeping and pressurization of the pipes progressively.

Given this, a schedule was developed for qualifications and start-up of the first section of 573 kilometers that join Tratayén, in Neuquén, with Salliqueló, in Buenos Aires.


The official schedule


June 20 | Enabling and commissioning of EMED Tratayén and enabling of kilometer 0 to 29.

June 25 | Enabling of kilometer 29 to 61.

June 27 | Enabling of kilometer 61 to 89.


@Energia_Ary@Energia_ArgOkannounce that the proposed objective has been met and next Tuesday, June 20, the valve will open and the filling process of the President Néstor Kirchner Gas Pipeline will begin, with the following schedule:pic.twitter.com/yMMumBG399– Argentine Energy (@Energia_ArgOk)June 15, 2023