Prime Minister Pham Minh Chinh inspects the Nha Trang expressway project

(PLO)- The Prime Minister requested that the project construction must ensure quality and progress; ensure occupational safety for workers and safety for people.

On the afternoon of January 26 (the 5th of the Lunar New Year), Prime Minister Pham Minh Chinh inspected and urged the Nha Trang – Cam Lam project under the East North – South expressway project phase 1; visited and wished Tet to officials and employees participating in the project.

The Nha Trang – Cam Lam component expressway project is more than 49 km long, passing through Dien Khanh, Cam Lam and Cam Ranh City (Khanh Hoa). This is one of three investment projects in the form of PPP with a construction period of two years and a payback period of about 16 years and four months.

Prime Minister Pham Minh Chinh visited and wished New Year to construction workers of Doc San tunnel. Photo VGP

The project has a total investment of more than 7,600 billion VND, of which the State’s participation is about 2,967 billion VND. Ho Chi Minh Road Project Management Board (Ministry of Transport) manages the project, Nha Trang – Cam Lam Expressway Investment Co., Ltd (Son Hai Group) is an enterprise investing in the project, expected to be completed in June. third quarter of 2023.

Belonging to Nha Trang – Cam Lam project, Doc San tunnel through Doc San mountain through Khanh Hoa province is one of the important “links” on the North-South expressway phase 1, with a length of 1,480 m/2 pipes. complete parallel tunnels (each tunnel is more than 700 m long).

Prime Minister Pham Minh Chinh inspects the Nha Trang - Cam Lam expressway project Photo 2

The ground clearance of Nha Trang – Cam Lam project has now reached 99.8%. Photo: VGP

According to the report, up to now, the ground clearance work of Nha Trang – Cam Lam project has handed over 49/49.1 km, reaching 99.8%. The project basically meets the schedule, the investor commits to shorten the schedule by three months. The output of construction and installation bidding packages from the beginning to date is about 2,786/4,345 billion VND (reaching 64.1% of the contract value).

The Project Management Board will continue to direct project enterprises and contractors to execute package 1 to make the most of favorable weather, to focus on machinery and equipment, to work overtime, to increase crews to speed up the construction progress. completion of the embankment work of the bidding package to construct the foundation, road surface… to meet the overall progress of the project.

The representative of Son Hai Group said that with the approval of the Prime Minister during the business trip last year, the enterprise applied new technology to construct the divider, which is more economical and safer. At the same time, the enterprise also spent more money to expand the curb compared to the design, making it safer, but the total project investment remained unchanged.

On the construction site, the Prime Minister praised the agencies, units, staffs and workers who have worked with the spirit of “through Tet”.

“The construction must ensure quality, progress, technicality, art and environment, ensure labor safety for workers and safety for people…” – emphasized the Prime Minister.

Prime Minister Pham Minh Chinh inspects the Nha Trang - Cam Lam expressway project Photo 3
The representative of Son Hai Group said that with the approval of the Prime Minister during the business trip last year, the enterprise applied new technology to construct the divider, which is more economical and safer. Photo: VGP

In particular, at the Doc San tunnel, the Prime Minister recalled that a year ago, during a business trip across Vietnam and during Tet, the contractor had just started digging through the mountain with many difficulties and challenges, so far the tunnel has been cleared. The Prime Minister was pleased, highly appreciated this effort and result, noted that businesses “say they do” and do effectively, the project is implemented quickly.

The Prime Minister wished businesses to develop more and more in the direction of high technology, becoming a large corporation, doing profitable business in the spirit of harmonizing benefits and sharing risks between the State, businesses and people.

The Prime Minister assigned the Ministry of Transport to immediately consider and resolve the recommendations of businesses, multiplying the good experiences and lessons that have been proven to be true; including the announcement of the 10-year route warranty, if necessary, amend or propose the competent authority to amend the regulations.

Prime Minister Pham Minh Chinh inspects the Nha Trang - Cam Lam expressway project Photo 4

The Prime Minister visited and wished Tet to engineers and workers under construction of the Nha Trang – Cam Lam expressway project. Photo: VNA

The Prime Minister emphasized the lesson of sticking to reality; study and amend regulations, criteria and standards to ensure objectivity, publicity and transparency in order to choose investors and good contractors who are qualified, enthusiastic, say they do, and avoid the situation of investors. , the contractor has had good works in practice but is not allowed to participate in the projects with the reason that they do not meet the standards and criteria, thus the standards and criteria are problematic.

“Without installation, group interests, how can people do things with their heads held high, openly and transparently, without having to run around at all,” said the Prime Minister.

The Prime Minister also emphasized that it is necessary to mobilize social resources in the form of public-private cooperation to develop the country. If only state resources are not enough, it is important to find a balance between the interests of the State, businesses and people, all win.

In the afternoon of the same day, at Thap Cham station, Ninh Thuan province, Prime Minister Pham Minh Chinh and the Government’s delegation attended the launching ceremony of the Nha Trang-Saigon railway upgrade project.

Also here, the Prime Minister, Deputy Prime Minister Tran Hong Ha and leaders of ministries, branches and localities together performed the launching ceremony to deploy the construction of the project to renovate and upgrade the Nha Trang-Saigon section of the route. iron Hanoi-HCMC.

The Prime Minister went to inspect and urge the expressway project

The Prime Minister went to inspect and urge the expressway project

(PLO)- The Prime Minister asked to pay attention to and take care of the resettlement for people, striving for a better life in the new place than the old one, and better next year than the previous year.

N.THAO (According to VGP)