Vilvoorde Viaduct Renovation: Traffic Disruptions and Phased Works Until 2031

2023-08-15 15:40:12

The renovation of the Vilvoorde viaduct has started and traffic on the Brussels inner ring will be disrupted from this Wednesday 16 August. The work will last eight years, until 2031.

1.7 kilometers long and 35 meters high, the viaduct was designed in the 1970s and opened to car traffic in 1978. Some 150,000 vehicles use it every day. Its structure is now in poor condition and its renovation has therefore become necessary. It concerns the overall structure of the bridge, its load-bearing structure and the interior of the building.

The objective is to maintain traffic on the viaduct as much as possible, with work divided into different phases. During each stage, only part of the bridge will be unavailable and traffic will continue on the other part, with a speed reduced to 50 km/h.

The first phase of the works will take place from August 2023 to the end of 2025, with disruptions on the inner ring and an impact on traffic towards Zaventem.

During the second phase, from spring 2026 to spring 2027, the work area will move in particular to the outer ring. Phases three and four, from spring 2027 to the end of 2030, will cause the greatest nuisance.

Eventually, thanks to the renovation, a fourth lane could be opened in each direction on the viaduct.