The Airports Corporation of Vietnam (ACV) has formally proposed delaying the completion of the first phase of Long Thanh International Airport to 2027 or 2028, citing construction and procurement obstacles that make the original 2026 deadline unattainable.
During a meeting on November 25, the state-run Airports Corporation of Vietnam (ACV) reported that while 88.63 per cent of the construction volume for the airport’s third component—which includes essential facilities—has been completed, the project cannot meet its contract schedule for this year. The company has disbursed 57 per cent of the contract value to date.
Construction Delays Stem from Labor Shortages and Procurement Issues
The project, which carries a total investment of nearly US$16 billion, has faced significant delays involving labor shortages and the procurement of materials. ACV identified that some construction items were initiated before technical designs were fully approved, while other materials and equipment were sourced from manufacturers or brands that differed from original contract specifications.
“Strictly penalize or report to competent authorities any contractors failing to honor contract terms,” Permanent Deputy Prime Minister Pham Gia Tuc directed during the meeting, according to reports from the government.

The Ministry of Construction has been tasked with auditing these discrepancies. Deputy Minister of Construction Pham Minh Ha urged the developer to review every modification to establish a legal basis for resolution, noting that the responsibility for quality inspection lies with the investor.
Revised Operational Outlook
Under the proposed adjustment, major infrastructure such as the passenger terminal, the first cargo terminal, and the parking garage are now slated to finalize construction or complete trial runs in June 2027. This shift follows earlier, more optimistic projections; in July, the Civil Aviation Authority of Vietnam had anticipated the facility would begin commercial operations on December 1, 2026.
A survey by the Civil Aviation Authority of Vietnam revealed that 34 international airlines have requested to postpone their transition from Tan Son Nhat International Airport to the new hub. Of these, 24 carriers aim to move during the winter 2027 flight season, while 10 others prefer to wait until summer 2028.
Airlines cited the need for six to 12 months to reorganize operations, including assigning flight crews and establishing ground handling services. International logistics firms, including UPS, FedEx, DHL, and Cargolux, have also indicated they require additional time for technical assessments regarding customs and cargo handling.
Meeting convened to resolve delays and set new deadlines
Permanent Deputy Prime Minister Pham Gia Tuc chaired a working session on November 25 with ministries, localities, and enterprises to remove bottlenecks and accelerate the first phase of Long Thanh International Airport, according to the Government Portal.

ACV assessed that objective and subjective factors prevent completing the entire third component in 2026 as contracted.
Materials and Equipment Deviate from Contract Specifications
ACV identified three main groups of difficulties during the meeting, including changes in materials, equipment manufacturers, brands, and types compared to contract specifications. Znews.vn reported that some items had been constructed and accepted based on approved construction drawings that did not align with the approved technical designs, while corresponding technical design adjustments had not been carried out. Other items were built before their construction drawing dossiers were approved.
The Deputy Prime Minister directed that violations be handled strictly according to authority and regulations, without legalizing wrongdoing or allowing new violations to arise, and ordered ACV to submit a comprehensive report on remaining workloads to the Government and the Ministry of Construction within one week.
Airlines and cargo operators seek later transition dates
Airlines said they need six to 12 months to adjust flight networks, assign aircraft and crew, and set up ground services, while also flagging risks to safety and service quality under simultaneous construction and operation conditions.
International logistics firms UPS, FedEx, DHL, and Cargolux have called for coordinated provision of express cargo terminals, customs facilities, truck handling areas, and connecting transport infrastructure, noting that preparation and technical assessments could take around 12 months. Vietnam Airlines and Vietjet representatives confirmed they are actively preparing resources to serve Long Thanh operations according to the competent authority’s plan and decision.

Airport Opening Contingent on Verified Safety Conditions
The government has mandated that the airport will only be permitted to open once all safety and technical conditions are verified. “ACV phải xác định rõ thời điểm công bố thông tin khai thác, kịp thời thông tin cho các hãng hàng không sau khi có thông báo của cấp có thẩm quyền để các hãng chủ động chuẩn bị nguồn lực, xây dựng kế hoạch khai thác và bố trí lịch bay,” said Phó Thủ tướng Thường trực Pham Gia Tuc.
The new Long Thanh International Airport is under construction in Long Thành ward, Đồng Nai city, approximately 40 km east of Ho Chi Minh City. Designed to relieve the severely overloaded Tan Son Nhat International Airport, which handled 40.7 million passengers in 2023 against a 30 million design capacity, the facility is critical for Vietnam’s aviation sector as the existing airport cannot be expanded further due to dense urban growth.
The project is developed in phases: the first phase, costing about US$4.6 billion, targets a capacity of 25 million passengers and 1.2 million tonnes of cargo annually with one terminal and one 4,000 m runway.
As the primary developer, ACV is required to submit a comprehensive report on the remaining workload to the government and the Ministry of Construction within one week of the November 25 meeting. Before December 10, the Ministry of Construction must then provide its own assessment to the government to facilitate a formal decision on adjusting the investment policy for the 336.63 trillion dong (about S$17 billion) Long Thanh Airport project.