FC Barcelona has finalized an agreement with Turkish construction firm Limak to complete the renovation of the Spotify Camp Nou.
The deal, confirmed by Mundo Deportivo, resolves months of negotiations regarding site timelines and secures the additional 300 million euros in financing approved by the club’s assembly on September 19.
The agreement marks a critical milestone for the club’s infrastructure strategy. By formalizing the remaining construction phases, Barcelona ensures that Limak retains primary responsibility for the site, while gaining the flexibility to delegate specific technical interventions to specialized subcontractors. This operational clarity is essential as the project moves into its most complex engineering phase.
The renovation’s most ambitious moment—the installation of the roof—is scheduled to begin following the conclusion of the current season. Engineers have already prepared the compression ring, setting the stage for the “Big Lift,” a massive operation to hoist the 3,000-ton structure. While the specific start date remains under review, the project timeline aims for completion during the second half of the 2027-28 season.
The club has secured the Estadi Olímpic Lluís Companys for the duration of the 2027-28 campaign to facilitate the ongoing work. The current plan dictates that the team will play the first half of the season at Montjuïc before transitioning back to the Camp Nou. Upon the return, the stadium will feature all three tiers fully accessible to supporters.
Initial proposals for a gradual reopening were discarded due to logistical complications. Authorities cited concerns regarding evacuation protocols and municipal permitting as primary drivers for the decision to wait until the facility is fully prepared for a total, three-tier opening. This decision prioritizes safety and operational efficiency over a phased return.
Despite the active construction, the stadium’s current capacity of 62,652 generates substantial revenue. The most recent league Clásico against Real Madrid generated 19.1 million euros in income, showing high market demand for premium matchday experiences.
The new club museum and official store are slated to begin operations early in 2027, as they are currently in the interior finishing stage. These additions are part of a broader push to modernize the site’s commercial footprint, which will culminate in the 2028-29 season.
During that year, the stadium is expected to operate with its full VIP suite capacity, coinciding with its selection as the host venue for the Champions League final—marking thirty years since the 1999 final between Manchester United and Bayern Munich.
| Project Milestone | Target Timeline |
|---|---|
| New Museum & Store Opening | Early 2027 |
| Camp Nou Return (3 Tiers) | Second Half of 2027-28 |
| Full VIP Capacity | 2028-29 Season |
The financial backing for these phases is now firmly in place, following the successful injection of the additional 300 million euros by investors. This capital injection, finalized earlier this month, provides the necessary liquidity to maintain the construction momentum required to meet the 2028 deadline for the European showcase event.
The club continues to coordinate closely with municipal authorities regarding the site’s integration into the surrounding urban landscape, ensuring that the stadium remains a viable venue for international events. With the contractual framework between Barcelona and Limak now settled, the focus shifts entirely to the engineering challenges of the coming summer.