Belgian Authorities Ordered Google to Halt Data Center Construction Near Charleroi

Belgian authorities in Wallonia ordered Google to halt construction of a data center near Charleroi on Friday, citing a “serious crime” after finding the project lacked a valid permit for its expanded scope and water-cooling plans, according to Spiegel. Greenpeace triggered the action with drone footage showing significant progress in November despite the permit withdrawal in August, according to spiegel.de and zdfheute.de.

Walloon officials said the building spans roughly three hectares — about 30,000 square meters — and that around 300 workers were on site when inspectors visited Thursday, ms-aktuell.de reported.

Belgian authorities force Google to halt data centre construction — NRT TV

Permit withdrawn after plans changed

Google secured an initial permit in 2024 for three air-cooled buildings. In 2025 the company applied to merge two structures into one larger facility and to draw cooling water from the Sambre river instead of using air cooling.

The Walloon administration approved the changes in April 2026, but Minister François Desquesnes reversed that decision in August after public objections, leaving the original permit in place only for the earlier, smaller design, ms-aktuell.de reported.

The affected building is located in Aiseau-Presles near Charleroi in the south of the country, ms-aktuell.de reported. The site sits on a former mining area in a business park spanning the municipalities of Farciennes, Aiseau-Presles and Sambreville, ms-aktuell.de reported. Authorities plan to forward a report on the violation to the public prosecutor, ms-aktuell.de reported.

Baustelle google rechenzentrum farciennes belgien
Photo: zdfheute.de

Greenpeace cites climate concerns

The organization supplied drone images showing construction well advanced in November, zdfheute.de reported.

Greenpeace alerted authorities to the case after drone footage showed construction had advanced significantly in November despite the withdrawn permit, zdfheute.de reported. The organization had announced the summary proceedings on Wednesday, zdfheute.de reported. Data center operators are required to publish their consumption, but few comply, a spokesperson for the Walloon regional authorities said, according to zdfheute.de.

Google's Belgian data centre stopped: built on a no? — PPC Land

Google pauses work, plans legal challenge

“We have stopped work in compliance with the instructions of the local authorities and pending further guidance,” a Google spokesperson told AFP. “We have been operating in Belgium for over 15 years and remain committed to complying with local laws.” The company has filed its own legal challenge against the minister’s August decision, with a public hearing set for January 7, 2027, before the Belgian Council of State, ms-aktuell.de reported.

Google told the Belgian news agency Belga it wants to continue a constructive dialogue with the regional government and experts about its investments in Wallonia, ms-aktuell.de reported.

Finland and Belgium stop Google data centre work — PPC Land

Broader European friction

The stoppage mirrors a similar clash in Finland, where authorities halted work at two Google data center sites in October until environmental impact assessments are completed, zdfheute.de noted.

Google had announced investments of one billion euros in April 2024 for the new Walloon site and expansion at Saint-Ghislain, then signaled an additional five billion euros for 2026–2027 in October 2025, ms-aktuell.de reported, according to Ms Aktuell. The financial impact and revised timeline for the Charleroi project remain unclear.

Charleroi is the largest city in Wallonia, located in the province of Hainaut, with a metropolitan population of 522,522 by 2008, making it Belgium’s fifth most populous urban area. Historically, the city thrived during the Industrial Revolution, becoming a hub for glass, steel, and coal industries, known as the “Pays Noir” (“Black Country”), which established its economic foundation and attracted European workers, fueling rapid population growth and labor movements that shaped its administrative landscape.

By the 1850s–1860s, Charleroi emerged as a critical center for labor strikes, reflecting its deep-rooted industrial significance and the region’s reliance on heavy industry, which continues to influence local planning decisions today.

The European Commission aims to at least triple EU data center capacity within five to seven years, with priority for sustainable facilities, ms-aktuell.de reported.