The committee overseeing the new Montpellier-Perpignan railway line confirmed plans for two new stations and a mixed passenger-freight route on November 17.
The decision specifies that new stations will be built in the Biterrois and Narbonnais regions. A line accommodating both passenger and freight trains will run between Béziers and Perpignan, with a tunnel to be bored under the Corbières massif to support these combined flows. Midi Libre reported that the committee also validated two funding conventions: “12 million euros for the continuation of studies and 6 million euros for land acquisitions.”
These amounts are expected to be voted on by the partner local authorities.
The project is divided into two phases. The first phase, from Montpellier to Béziers, was declared a matter of public utility in February 2023. According to debatpublic-transports-vral.org, this phase involves 52.3 km of new track and 7 km of connecting lines and is scheduled to begin construction in 2029, with a targeted opening in 2034. This section is expected to reduce travel time by 18 minutes.
The second phase, from Béziers to Perpignan, is still under discussion. This section covers approximately 100 km and is planned for a later horizon, around 2040. A concertation publique for this phase is planned for the spring of 2026. When initially submitting the project to the National Commission for Public Debate, the project owner announced costs of 3.2 billion euros for phase 1 and 7.1 billion euros for the entire project. A technical file, including environmental, financial, and territorial assessments, is expected to be finalized by the end of 2028.
For the first phase, the financing is shared between the State (40%), local authorities (40%), and the European Union (20%). The local authorities’ financial contributions are managed through the Société de la ligne nouvelle Montpellier-Perpignan (SLNMP), which was established in 2022. This society can borrow funds and collects a special equipment tax. The local authorities have committed funding which will be disbursed through 2028. The market for the design and construction of the first phase is valued at 1.634 billion euros excluding taxes. In 2026, a funding convention of 68.6 million euros was established to finance the preliminary studies preceding this market, to which the European Union has already contributed 22.5 million euros. The committee of pilotage, which met on November 17, validated these financial arrangements.
The precise locations for the two new stations remain undecided. In the Biterrois, the long-awaited station for Villeneuve-lès-Béziers, supported by Mayor Aurélie Pace and the Agglo Béziers Méditerranée, is being considered. So is a site in Nissan-lez-Ensérune, a proposal that was initially rejected in 2012 but has been revived. Studies are ongoing for both potential locations, Midi Libre noted.
“This choice will make it possible to ‘de-saturate the coastal axis, one of the most saturated in France, develop rail freight to promote the shift of goods from road to rail, and free up new capacities for our daily liO trains,'” said Carole Delga, president of the Occitanie region, as quoted by Midi Libre.”