Construction has officially begun on the Greater Dublin Drainage Project at the Clonshaugh site, a sewage treatment scheme scaling up to a cost of €2.3 billion, RTÉ reported.
The infrastructure project will service north Dublin along with parts of Meath and Kildare, providing wastewater treatment capabilities for half a million people. Uisce Éireann states the development will ultimately unlock capacity for up to 185,000 new homes across the capital region.
Planning for the massive wastewater scheme began two decades ago, during which time projected costs have quadrupled. Preliminary works are already underway, with the plant expected to become operational by 2031.
“The cost of delay is very significant across all capital projects, and that’s why we need to promote and accelerate delivery in all elements of how we plan and deliver projects,” said Minister for Finance Jack Chambers at the turning of the sod ceremony.
The engineering undertaking involves a 25km underground pipeline running from Blanchardstown to transport wastewater to the main treatment facility at Clonshaugh. Once treated, the water will travel through a 6km marine outfall pipeline extending from Baldoyle to a discharge point northeast of Ireland’s Eye.
“It will create essential capacity and strengthen services across the region and will up capacity at the Ringsend plant,” said Uisce Éireann CEO Niall Gleeson.
Minister for Housing James Browne described the project as a critical milestone for housing delivery. “Our infrastructure needs to grow to meet the need going forward,” he said.
Infrastructure Delivery Director Maria O’Dwyer said that the overall capital expenditure will range between €1.9 billion and €2.3 billion. Main construction works are scheduled to commence at the end of next year or in early 2028.
“Today marks the culmination of years of careful planning, design and consultation to ensure that this project can meet the housing needs of the people of Dublin and surrounding areas now and for the future,” said Taoiseach Micheál Martin.
Uisce Éireann originally submitted planning applications to An Bord Pleanála in June 2018. Although permission was granted the following year, the development became bogged down by a succession of legal challenges.
The planning board issued a final green light in July 2025, though an additional challenge was subsequently lodged by a company named Wild Irish Defence. Uisce Éireann and Wild Irish Defence reached an out-of-court agreement last December, clearing the path for the current tendering and construction phase.