DPWH Targets Full Opening of Mindanao Avenue Extension by February 2027

The Department of Public Works and Highways (DPWH) targets a full opening of the long-stalled Mindanao Avenue extension in Caloocan City by February 2027, with three lanes opening this December 2026, Public Works Secretary Giovanni Lopez said Sunday.

The 3.2-kilometer project will link North Caloocan to the North Luzon Expressway (NLEX) and Quezon City, providing an alternative to congested routes in the area, the Philippine Daily Inquirer reported.

Decades of right-of-way delays

Construction began in the 1980s but stalled for nearly five decades due to right-of-way (ROW) problems, Lopez said. Only 1.4 kilometers were completed and opened between 1980 and 2014, according to the Manila Times. Work resumed in 2017 with the National Housing Authority and local governments addressing relocation of informal settler families along the alignment, the same outlet reported.

Marcos orders faster work on Mindanao Avenue Extension for full opening in February 2027 — Manila Standard

Presidential directive accelerates timeline

President Ferdinand Marcos Jr. ordered the DPWH to fast-track the remaining section to ease traffic between Quezon City and Valenzuela City. “It is only now that this right-of-way issue has been resolved. The President gave us strict instructions that this must be completed,” Lopez said.

The DPWH opened a 700-meter segment from P. Dela Cruz Street in Caloocan to MGM Road in Valenzuela in April 2018, built by Tokwing Construction Corp. under a contract valued at approximately P118 million, the Manila Times reported. In 2024, portions in Caloocan opened to light vehicles with truck restrictions still in place.

Senate approves 2027 budget with project funding

The Senate concluded deliberations on the proposed ₱7.2 trillion budget for 2027, which includes funding for the extension, The Chronicle reported. Tokwing Construction also handled Segment 2C, Phases I and II, with the Constructors Performance Evaluation System listing the contract at approximately P68.978 million in the third quarter of 2019.

The DPWH has not yet released updated figures on the project’s overall accomplishment rate, remaining ROW requirements, or a revised completion target, the Manila Times noted.