The ELWIND offshore wind project concluded its initial public consultation meetings on November 6, 2026, after engaging with residents in Ventspils, Pāvilosta, and Ziras, according to Ecomagazine.
The joint Latvian-Estonian initiative drew approximately 170 participants, including local residents and municipal representatives. Discussions focused on the project’s potential environmental impact, the development of onshore cable corridors, and the anticipated economic benefits for coastal communities.
Project representatives and researchers briefed attendees on the progress of ongoing studies, which involve more than 20 separate environmental and technical assessments. These studies aim to provide data regarding the Baltic Sea’s biodiversity, geology, and environmental conditions, as well as the potential impact of turbines on birds, fish, and marine mammals.
“Our aim is to ensure that offshore wind energy development also creates opportunities for Latvia’s coastal areas. Local residents understandably want to know what the tangible benefits will be,” said Jānis Ločmelis. He said that specific details regarding job creation or port investments remain dependent on future technical solutions and study results.
The project’s potential economic contribution was a frequent topic of discussion during the meetings. Regulatory requirements mandate that wind power producers pay EUR 2,500 per megawatt (MW) of installed nominal capacity annually to support local community development.
The Latvian portion of the ELWIND project has a potential capacity of 500–1,000 MW. Based on these figures, annual payments to local municipalities could range from EUR 1.25–2.5 million once the wind park becomes operational.
The designated study area for the Latvian portion of the project is located in the Baltic Sea between Liepāja and Ventspils, at a distance of 22–30 kilometers from the coast. In 2025, planners moved this area more than seven kilometers further offshore to avoid potential marine protected areas and reduce risks to biodiversity.
Oskars Beikulis, Lead Consultant at SIA “Estonian, Latvian & Lithuanian Environment”, said that the environmental impact assessment is a strictly regulated process. The procedure is designed to establish baseline conditions, identify potential adverse impacts, and propose measures to prevent or reduce them.
While in-person meetings have concluded, the public consultation process remains open for written proposals until November 13, 2026. Submissions may be sent to the State Environmental Service via email to [email protected] or by post to 23 Rūpniecības iela, Riga, LV-1045, Latvia.