Far North Solar Farm Placed Into Receivership After Consenting Issues

Far North Solar Farm Ltd, the company behind a proposed 40-megawatt solar farm on the northern shore of Lake Benmore, was placed into receivership on November 18.

Aquila Clean Energy SG Holdco Pte. Ltd appointed Stephen Keen and Stephen White of Teneo Financial Advisory New Zealand as joint receivers under a General Security Deed dating from a 2021 joint venture agreement, 1News reported.

The deed covered a partnership that commissioned the Pukenui solar farm in Northland before the venture was disbanded in January so both parties could “pursue their perspective strategic priorities independently,” according to Aquila’s website. Far North Solar Farm retained developments in Greytown, the Mackenzie and other South Island areas.

The receivership follows a turbulent consenting process for The Point project. The company lodged its fast-track application on September 1, 2025, deemed complete on October 16, Chris Lynch Media reported.

In August, director Richard Homewood informed the fast-track panel that the company would not settle outstanding invoices, explaining that withholding payment was the only way to gain additional planning time before an August 31 deadline for expert ecological information. The Environmental Protection Authority subsequently suspended the application with no timeframe set for repayment.

Photo: Chris Lynch Media

A Far North Solar Farm spokesperson defended the move at the time, saying the company intended to pay its fees and progress the project. However, Mary Murdoch, a spokesperson for a Twizel community group, accused the developer of misusing the legislation. “They do appear to be gaming the system and not using it as intended,” Murdoch said in October. Far North Solar Farm firmly denied the characterisation.

Newsroom reported the company never received any of the $78 million loan facility committed by New Zealand Green Investment Finance (NZGIF) in 2024. The facility covered five developments intended to generate around 1.13 gigawatts.

Richard Homewood said then that the deal would allow the company to rapidly accelerate development of new generation, telling RNZ’s Morning Report that most sites would be under construction within 12 to 18 months, but projects never got off the ground. NZGIF was established in 2018 to fulfil a commitment in Labour’s confidence and supply agreement with the Green Party.

Far North Solar Farm also developed a 144-megawatt proposal at Waipara Flat Road in North Canterbury, where independent hearing commissioners granted partial resource consent last month. The consent attracted 158 submissions, 125 opposed, and an appeal was lodged by Waipara Valley Community Collective Incorporated on November 3, Chris Lynch Media reported.

A 175-megawatt solar farm near Greytown received resource consent in June subject to considerable conditions, while a consent application for a project near St Arnaud in the Tasman district has had its base deposit fee unpaid for more than two years, Newsroom reported.

“A sustainable growth coalition might be the way to go. Small groups doing research and getting independent expert advice to put to the fast-track panel,” Murdoch said in August. “People are not happy about what’s going on.”

Photo of author

Newsroom

Newsroom at Archyde.

Over 1,087 Russian Soldiers Died by Suicide Since Ukraine Invasion, Leaked Data Shows

Romania’s Idle EV Fleet Could Power Homes and Grid, PPC Blue CEO Says