The U.S. Department of Energy committed a $2.8 billion conditional loan to Grid United on Tuesday for a $4 billion, 106-mile transmission line that will double power transfer capacity between the eastern and western grids across Wyoming.
The Wyoming Intertie will run from the Laramie River Station coal plant near Wheatland to the Aeolus substation near Medicine Bow, creating a bidirectional link that Energy Dominance Financing Director Gregory Beard said “strengthens the grid and gives operators new tools to respond to surges in demand or outages.”
Wyoming sits in the Western Interconnection, with the seam between the two grids tracing the state’s eastern border, making the Laramie River Station — one of few plants with access to both systems — a logical anchor point, Wyoming Energy Authority Director of Energy Market Development John Jenks told WyoFile.
Construction is slated to begin in 2030 and take three years, contingent on finalizing land rights and regulatory approvals across a route that Beard described as roughly 90 percent state and federally owned land, minimizing eminent domain risk.
The DOE projects the line will save ratepayers in Wyoming and 17 other states a combined $39 billion in avoided costs over 30 years, though Jenks cautioned the intertie “won’t necessarily lower rates for Wyoming customers” but could dampen price spikes during supply imbalances.

Federal Loan Covers 70% of $4B Project
- Federal commitment: $2.8 billion conditional loan covers 70 percent of the $4 billion project cost under the Energy Dominance Financing program.
- Grid impact: Doubles east-west transfer capacity, enabling bidirectional flow across the Western Interconnection seam at Wyoming’s eastern border.
- Timeline risk: Construction start targeted for 2030; route finalization, tribal consultation, and multi-jurisdictional permitting remain unresolved.
Federal Program Backs 70% of Project Cost
The Energy Dominance Financing program, established under President Donald Trump’s executive order on grid reliability and security, provides the conditional loan to Houston-based Grid United. The $2.8 billion federal backstop represents 70 percent of total capital expenditure, leaving Grid United to raise the remaining $1.2 billion in equity or subordinate debt.
DOE officials did not disclose the loan’s interest rate, maturity, or covenant structure in Tuesday’s announcement. The conditional nature of the commitment means final disbursement hinges on Grid United satisfying permitting, land acquisition, and commercial offtake milestones.
Market Access for Wyoming Generation
“It adds flexibility to energy being dispatched onto the grid,” Jenks said. “We can send electricity east if we have excess electricity, or we can take it from the east. For Wyoming electricity producers, it’s expanding the markets to dispatch and sell their electricity.”
The intertie does not add generation capacity but enables new renewable and thermal projects by de-risking off-take to either grid. Beard noted “growing electricity demands nationwide and on both sides of this interconnect,” framing the line as a prerequisite for future capacity additions rather than a standalone solution.
Route Ownership Claims Differ Between Sources
Grid United’s Wyoming Intertie website states the route consists of about 90 percent private property, while Beard characterized it as 90 percent state and federally owned land in remarks reported by the Associated Press. The discrepancy matters: federal and state land routes typically follow NEPA review and Bureau of Land Management rights-of-way processes, whereas private land requires negotiated easements or eminent domain proceedings.
Beard asserted “this is not going to have issues around land acquisition or condemning properties” and predicted no protests. Grid United confirmed it is still working with tribal nations and landowners to finalize the alignment, which “will remain proposed until it receives approval from county, state and federal regulatory bodies.”
| Metric | Figure | Source |
|---|---|---|
| Total Project Cost | $4 billion | DOE / Grid United |
| Federal Conditional Loan | $2.8 billion | Energy Dominance Financing Program |
| Projected Ratepayer Savings (30 yr) | $39 billion | DOE Estimate |
| Construction Start Target | 2030 | DOE / Grid United |
| Line Length | 106 miles | DOE / Grid United |
Cost Allocation Method Remains Undefined
The $39 billion avoided-cost figure spans 18 states and three decades, but the allocation methodology — whether costs are socialized across transmission customers or assigned to beneficiaries — remains undefined.
Jenks said the line “can dispatch generation resources more efficiently, which should — in theory — lower electricity bills,” adding, “It might be a stretch to say it will [lower monthly bills], but that’s the theory behind it.” FERC Order 1000 regional planning processes will ultimately determine cost recovery mechanisms, a proceeding that could extend past the 2030 construction target.
Grid United says construction will commence after the project secures land rights and regulatory approvals.