FOI Request Reveals Dún Laoghaire-Rathdown Council Spent Nearly €1m on Halted Social Housing Project

A Freedom of Information request in Dublin 18 revealed that Dún Laoghaire-Rathdown County Council spent nearly €1 million on a halted social housing development that ultimately required complete rebuilding. The project, initiated in April 2021, faced severe delays before its original contract was terminated.

Council Terminates Contract After Delays

Although construction was scheduled for completion by February 2022, the council issued a warning letter the following month regarding severe delays.

The developer blamed a sick foreman and difficulties in securing labor and reliable subcontractors. These issues persisted, and the developer received notification of contract termination in August 2022, as detailed by The Journal. Records show the council paid the contractor €984,341 before ending the agreement.

Emergency Costs Climb as Site Deteriorates

Following termination, the incomplete site sat vacant for more than eight months while consultant engineers inspected the structures. Engineers determined that exposure to the elements required the complete removal of timber frames and insulation in one block, while sunlight exposure necessitated replacing drainage pipes in another.

To address urgent health and safety risks, the council hired an emergency contractor in October 2022 for an initial €142,988. Subsequent site issues pushed this emergency cost to €195,652 in March 2023 and €229,702 by July 2023, driving total incomplete project spending past €1.2 million.

Photo: jrnl.ie

Details Through Public Records

Conor O’Carroll reported in The FOI Files, a series from The Journal Investigates, that a local resident named Liam filed freedom of information requests after noticing construction had stalled near his home. According to The Journal Investigates team, the records obtained through this inquiry revealed the timeline and documents detailing how the Dún Laoghaire-Rathdown County Council project fell apart.

The Journal Investigates reported that correspondence between the council and the developer outlined severe obstacles on the site. The developer cited issues with a sick foreman and “difficulty in sourcing labour to manage and carry out the works,” alongside ongoing struggles to secure “solid commitments from sub-contractors” that pushed completion dates further away.

Despite individual setbacks, Dún Laoghaire-Rathdown County Council advances a much broader social housing programme. As part of an active pipeline exceeding 1,000 homes progressing through various stages of development across the county, the organisation utilises the Competitive Dialogue process to transform council-owned land into sustainable residential communities.

Department Approves Revised Six-Million-Euro Budget

In March 2024, Dún Laoghaire-Rathdown County Council submitted a revised budget of over €6.3 million to the Department of Housing, averaging €486,143 per unit. While the Department considered this price tag high, officials accepted the figure due to the original contractor’s failure, emergency site works, and completion expenses.

A second appointed contractor finished the construction and handed the project back to the council in September. A spokesperson for Dún Laoghaire-Rathdown County Council told The Journal that all payments were “made in accordance with the contract”.

Photo of author

Entertainment Desk

Entertainment Desk at Archyde.

YouTuber Memeio Unlocks Playable Vice City Portal in GTA 6

Drunk Street Musician Forces Entry at Iwan Fals’ Depok Home, Police Intervene