Transport and Investment Dávid Vitézy announced a 21-kilometre renewal of the No. 60 line built to 100 km/h standards. Travel times on the Pécs–Nagykanizsa–Szombathely rail corridor are set to shrink after Transport and Investment Dávid Vitézy announced that a 21-kilometre renewal of the No. 60 line will begin next year.
- The work covers two sections totaling 21 km between Gyékényes–Berzence and Középrigóc–Darány.
- Line speed will rise from 40–60 km/h to 100 km/h once track is renewed.
- First phase trims about five minutes; signalling upgrade planned for 2028 adds another four to five minutes.
- Procurement tender to be published this week; budget hike from 30 to 80 billion forints enables the project.
Two sections, 21 kilometres
The renewal targets the Gyékényes–Berzence stretch of 15.5 kilometres and the Középrigóc–Darány stretch of 5.6 kilometres. Both carry Pannónia InterRégió services that currently crawl at 40–60 km/h because of degraded track.
Contractors will lay new rails with a gapless track, perform mass concrete joint replacement and ballast tamping, and, where needed, repair the substructure. Nine level crossings will be rebuilt, drainage culverts cleared and three railway bridges waterproofed and repaired.
Speed gains in two steps
Vitézy said the track work alone should cut journey times by roughly five minutes. A second phase — modernising signalling, including the installation of light signals and equipment to exclude oncoming traffic — is scheduled from 2028 and promises a further four to five minutes on InterRégió runs between Pécs, Nagykanizsa and Szombathely, according to Globalhir. The renewed alignment is being built to 100 km/h standards.

Funding unlocked by budget increase
The government raised MÁV’s 2027 investment envelope from 30 to 80 billion forints, making the tender possible this week and construction next year. Vitézy wrote on Facebook that the line “has long been ripe for renewal” and that the money is finally available.
Separate Budapest–Pécs plan stays in design
Vitézy also launched preparatory studies for a comprehensive overhaul of the Budapest–Pécs main line (No. 40), aiming for hourly InterCity services and barrier-free stations, with construction eyed for the 2028–2034 EU funding cycle. That project remains years away, while the No. 60 renewal moves to procurement immediately.