The International Energy Agency’s annual World Energy Outlook, published Thursday, warns that AI data centers could saturate electric grids in major markets. Fewer than 100 large AI sites already equal 50 GW of power, and announced projects exceed today’s peak electricity demand in some of the world’s biggest economies.
The grid, not the generator, is the bottleneck. That is the core finding of the IEA’s World Energy Outlook, which used satellite observation to track 93 large AI computing sites whose capacity has grown tenfold in two years, according to Selectra.
Here is the calculation. In several of the world’s principal markets, the IEA found, the power capacity of announced projects already exceeds today’s peak consumption. The report does not name which markets, nor where the 93 sites sit.
IEA projects $4 trillion data center spend by 2030
- Data centers absorbed $565 billion (about €515 billion) of investment in 2025; cumulative spending reaches $4 trillion (€3.65 trillion) by 2030, with three-quarters of the growth coming from AI, not storage or streaming, per the IEA.
- The binding constraint is connection time: a data center takes two to three years to build, a high-voltage line roughly twice that, and transformer and cable suppliers already have full order books.
- In Italy, connection requests to Terna’s transmission grid exceed 100 GW against a national peak of 57.98 GW, yet Terna expects only 1.5–2 GW actually operating by 2030.
Ninety-three sites, one country’s worth of power
Satellite imagery let the IEA count what corporate disclosures often blur: massive, concentrated computing campuses. In two years, capacity at the 93 tracked sites grew tenfold. The world’s data centers consumed roughly 500 TWh in 2026 and, in the agency’s central scenario, reach about 1,000 TWh by 2030, double today’s level.

The IEA identifies three compounding pressures: concentrated load in a handful of regions, shortages of transformers, cables and copper, and local resistance from residents who fear higher bills.
According to the IEA, the world needs at least 25 million kilometers of new transmission lines over the next decade, plus another 15 million kilometers replaced or upgraded.
The timing mismatch pricing in delay
A data center completes in two or three years. A high-voltage line or substation takes about double. That asymmetry means projects queue for grid access regardless of how much generation exists, and the IEA’s saturation scenario assumes every announced project actually gets built, a condition Selectra notes remains far off given the gap between Italy’s 100 GW requested and the 2 GW expected.
In the United States, rising electricity prices compared with 2024 and the data center buildout became themes of this year’s midterm election campaign, Selectra reported. In Spain, the government is studying a requirement that new computing centers use green energy, with the stated aim of protecting households.
“Dietro l’apparente leggerezza di una risposta istantanea generata dall’intelligenza artificiale si nasconde un consumo vorace di elettricità, acqua e terra.”
That framing belongs to coverage from the COP31 summit in Antalya, where AI’s infrastructure footprint was placed on the negotiating table, according to Vatican News. The Turkish presidency proposed a pact tying data center growth to renewable sources and full transparency. Vatican News credits AI with real climate benefits (monitoring deforestation, optimizing grids, predicting extreme weather) while noting its campuses increasingly absorb land, energy and water.
Italy’s 100 GW of requests against a 58 GW peak
| Indicator | Value | Source |
|---|---|---|
| Connection requests to Terna’s transmission grid (August 31, 2026) | 553 applications, 101.36 GW | Terna via Selectra |
| Initiatives approaching October 2026 | Near 600 | Selectra |
| National peak demand (July 15, 2026) | 57.98 GW | Terna via Selectra |
| Data centers expected in service by 2030 | 1.5–2 GW | Terna |
| Global data center consumption by 2030 | About 1,000 TWh (2x today) | IEA |
Applications filed on Terna’s Econnextion portal exceed the country’s entire peak demand by nearly two-to-one. Terna, Italy’s transmission system operator, treats most of that volume as speculative, expecting just 1.5–2 GW of actual capacity by 2030. Requests were still climbing; the Selectra report noted initiatives approaching 600 as of October.
Emissions rise while the tech giants buy green
Renewables cannot scale fast enough to cover the growth, so gas and coal plants fill part of the gap. Data center emissions rise 70% by 2030, despite the major technology groups’ renewable power purchases. As a share of global consumption, though, they stay modest: the growth in air conditioning demand by 2035 alone would exceed the total for all data centers.
Three-quarters of the investment surge is AI-driven, per the IEA, a shift from the storage and streaming workloads that built most of today’s facilities.
Who pays for the wires
For households, the cost arrives indirectly. Grid upgrades land in the transmission component of the bill, and higher demand pushes wholesale prices up. The IEA report does not quantify the share of the increase attributable to data centers. Italy’s ARERA reference price for vulnerable customers stands at 43.43 eurocents per kWh, taxes included, for the fourth quarter of 2026, effective from October 1.
The saturation scenario is a timing problem, not an arithmetic one: generation exists or can be built, but connection queues, transformer backlogs and permitting delays stretch projects from years into a decade.
Neither the IEA nor Terna says when that gap closes, and the report is careful to say the saturation risk assumes full delivery of every announced project, a condition the Italian 100-GW-versus-2-GW gap shows how far away that condition is.
Until the buildout of lines catches up to the buildout of campuses, the IEA’s 50 GW of tracked capacity keeps accumulating in front of a grid that cannot take it yet.