Singapore has approved 3.4 GW of clean power imports from Indonesia — roughly two-fifths of the city-state’s today’s peak.
Why it matters now: the power is meant to underpin Singapore’s entire energy transition. Meanwhile, Singapore wants gas — which generates about 95% of its electricity today — cut to half the mix by 2035. Without Indonesian electrons, the math gets harder.
The work was real. Chief executive Frank Phuan told bneGREEN the work is now on hold.

“It’s going to be some sort of a benefit to Indonesia, right?” Phuan said. “But how is that price being calculated? Is it inclusive of all sorts of transmission charges or just pure generation?”
ERA is not alone. Every one of those developers now carries political risk stacked on top of the engineering risk, with no agreed price formula to anchor their models.
Indonesia’s bargaining position rests partly on how little solar it has built at home. President Prabowo Subianto’s government has floated a 100 GW solar goal, and Jakarta argues a higher export price could help pay for domestic generation.
The problem is what rivals charge. Singapore, patiently, is comparing notes.
| Project | Approved capacity | Developers | Status |
|---|---|---|---|
| Strait cable solar export | 400 MW (of 2.2 GW planned) | Equator Renewables Asia | On hold |
| Conditional approval | 600 MW | PacificLight Power, Salim Group | Waiting on price |
| Conditional approval | 1 GW | TotalEnergies, Royal Golden Eagle | Waiting on price |
| Total EMA-approved imports | 3.4 GW by mid-2030s | — | Stalled |
Exports could earn Indonesia IDR19 trillion ($1.04bn) a year if a deal is struck. Singapore, in turn, has pressed plantation companies over the haze from Indonesian fires, with Wong saying it was weighing legal action.
The Jakarta Post reported on November 16 that the delay risks derailing the solar projects themselves, raising questions over developers’ willingness to build plants without confirmed buyers. The Post said that Indonesia could not yet export electricity, and that the authority to set export prices rests with the state, which is negotiating a “mutually beneficial price agreement.”
He said it remained unclear how long the delay would last.
Singapore, for its part, is not without alternatives. Singapore also holds provisional deals for more than 4 GW of imports from Australia and Malaysia, and it has shown a habit of diversifying rather than waiting. As the Jakarta talks drag on, the 3.4 GW at stake looks less like a prize and more like a bargaining chip that may expire.
Exports could earn Indonesia IDR19 trillion ($1.04bn) a year. Malaysia’s solar bids are a third of Indonesia’s costs. The next figure to watch is the one neither government has published: the surcharge.
Worth a look
- Obama Urges New House Democrats to Contest Ground Everywhere
- Wyoming Students Show Gains in Math, English, Science as Enrollment Falls 4,500 Since 2019
- Review: The Whyte Sythe RS Delivers High-End Suspension at a Reasonable Price – Pinkbike (newsdirectory3.com)
- Storm Cuts Power to 48 Settlements Across Northwest Bulgaria (newsy-today.com)