It leaves the Nuevitas thermoelectric system once more 2024-05-16 08:44:02

Unit 6 of the “Diez de Octubre” thermoelectric plant (CTE) in Nuevitas, within the province of Camagüey, was as soon as once more out of service.

This unit had been on technical shutdown for upkeep for 77 days and couldn’t stabilize its providers for twenty-four hours synchronized with the Nationwide Electrical System (SEN).

The reality is {that a} day earlier than the occasion, its synchronization with the SEN after “corrective actions” had been introduced on nationwide tv. However, this Tuesday the report from the Electrical Union of Cuba (UNE) reported the breakdown of unit 6 of the CTE Nuevitas.

What work was carried out on this unit?

In keeping with a report broadcast on the Cuban Nationwide Tv Information, that block acquired corrective actions, primarily within the boiler space.

Subsequently, the 77-day shutdown made it potential to resolve faults in computerized tools and turbine components.

It occurs that the reestablishment of machine 6 would cut back blackout occasions and improve the steadiness of the system within the heart and east. All this even if stated unit doesn’t totally cowl the deficit in era capacities that the UNE faces.

In the meantime, some specialists identified the constructive values ​​expressed by the machine after synchronization, as well as, the boiler was a precedence in upkeep.

Likewise, it was potential to alter the entire economizer, due to a component manufactured by operators of the CTE Felton of Holguín. This was said by engineer Orlando Anazco Ponce de León, brigade director of the Nuevitas Energy Plant Upkeep Firm.

Six turbine bearings that already wanted it had been additionally repaired. Whereas within the Regenerative Air Heaters (CAR) a number of vital repairs had been achieved and the alternative of all CAR baskets.

Likewise, intervention was carried out on the regulation valve quantity 3 of the turbine, which was broken, and work was carried out on the regulating system and its cleansing.

Nonetheless, lower than 24 hours after synchronizing the SEN, they had been already reporting the system output of unit 6 of Nuevitas. Subsequently, no particulars had been supplied about this departure, limiting itself to the recurring explanation for the breakdowns.

#leaves #Nuevitas #thermoelectric #system