Labrecque, a village of 254 affected households in Quebec’s Lac-Saint-Jean region, has launched a public tender for a wastewater treatment system estimated at more than $30 million — a project 35 years in the making that will finally stop untreated sewage from flowing into the Mistouk River, according to Radio Canada.
Construction is expected to begin in May 2027, with service starting in 2028.
That $30-million figure carries weight beyond its size. For most of three and a half decades, the municipal network’s wastewater has been discharged into the Mistouk with no treatment at all — a situation Radio-Canada describes as now requiring correction to meet government environmental requirements. The tender was authorized by council at its regular meeting on November 2, Le Lac-St-Jean and Radio-Canada both reported this month.
Why does untreated wastewater matter to health? Raw sewage carries enteric pathogens — bacteria, viruses and parasites that infect the intestinal tract — along with nitrogen and phosphorus that fuel algal blooms and oxygen depletion in receiving waters.
Aerated lagoon systems, the type Labrecque will build, treat effluent through sustained biological digestion in large basins rather than high-energy mechanical plants, a method long used by small Quebec municipalities. Chemical dephosphatation, which the planned station includes, removes phosphorus that would otherwise over-fertilize the river.
Sewage to Flow into Aerated Lagoons Instead of River
- Until now, Labrecque’s sewage has gone into the Mistouk River raw — no treatment step of any kind.
- The new system uses lagoons: natural bacteria break down waste in aerated basins, and chemicals strip out phosphorus.
- Eighty percent of village streets will be dug up and rebuilt to separate storm water from sewage, so the treatment plant isn’t overwhelmed by rain.
What the $30 Million Buys
Le Lac-St-Jean reported the tender’s scope in detail. Crews will open and re-close sections of roughly 80 percent of the streets in the urban perimeter to upgrade underground infrastructure. Nine outfall pipes will be built, and various culverts replaced. Two pumping stations — one underground, one in a building — will move sewage to purification basins south of the village, each fitted with a force main, an overflow pipe and a check-valve chamber.
The treatment station itself will be of the aerated lagoon type, with an access road, aeration basins, an outfall pipe, the chemical dephosphatation system and a service building, Le Lac-St-Jean reported. The full work plan is set out in a public notice on the municipality’s website and Facebook page.
The Numbers Behind the Project
| Measure | Figure | Source |
|---|---|---|
| Estimated project cost | More than $30 million | Le Lac-St-Jean; Radio-Canada |
| Streets rebuilt in urban perimeter | About 80% | Le Lac-St-Jean |
| Households affected | 254 | Radio-Canada |
| Years the project has been discussed | More than 35 | Radio-Canada |
| Usual subsidy envelope to be exceeded | 80% | Le Lac-St-Jean |
Repeated delays have driven costs up each time, Mayor Marie-Josée Larouche told Le Lac-St-Jean. “We’re really happy to have been able to launch the call for tenders after so much work and waiting,” she said — a remark translated from the French original.
Radio-Canada, which interviewed Larouche separately, reported her framing of the timeline. “It’s work that’s been going on for 35 years. There have been efforts, regulatory changes, deferrals… So we’re really happy that finally this project can be carried out,” she told the broadcaster. On residents’ expectations: “I think citizens expected it to be postponed again, but now it’s official.”
Who Pays, and What Residents Should Expect
The subsidy question remains open. Le Lac-St-Jean reported that the subsidized proportion should be set in January — and that with a $30-million price tag, the envelope will have to exceed the customary 80 percent. Larouche assured Radio-Canada that provincial and federal grants will cover the large majority of the work, with cost-sharing for directly connected residents still to be worked out once tenders close.
Practically, residents face two to three years of disruption: trenching across most streets, upgraded water and sewer networks, and some sidewalks and aging roads renewed, Radio-Canada reported. The municipality will hold information sessions on the work phases. The mayor also linked the project to growth — new streets and new houses have been on hold, she noted, because the existing network couldn’t support them.
Waterborne Risk and When It Matters for Health
For residents of Labrecque, the health relevance is indirect but real: municipal drinking water and recreational use of the Mistouk both depend on the river not functioning as an open sewer. This story contains no immediate clinical action items — no boil-water advisory has been issued, and none is reported by either outlet.
Residents with concerns about water quality or water-related illness should contact their local public health office (the CIUSSS serving the Saguenay–Lac-Saint-Jean region) rather than self-diagnose. Anyone experiencing gastrointestinal symptoms after contact with surface water should seek standard medical care; this project changes infrastructure, not individual treatment.
What remains unsettled, per the sources: the subsidy percentage (January), the winning bidder, and the exact phasing of street work.
Labrecque is a young municipality by Quebec standards: the first settlers arrived only in 1917, the township was proclaimed in 1920, and the municipality was incorporated in 1925. It was named after Michel-Thomas Labrecque (1849-1932), the third bishop of Chicoutimi, and its first industry, a sawmill, began operating in 1921. A century later, the village counted 1,328 residents in the 2021 census — meaning the wastewater project will touch a substantial share of its 575 occupied dwellings.
For a village that has debated this since the late 1980s, the next milestone is concrete: tenders now, a funding decision in January, and shovels in the ground in May 2027. “I think everyone will be very happy, finally, to be able to carry out this major project here at home,” Larouche told Radio-Canada.
References
- Le Lac-St-Jean: “30 M$ pour l’implantation d’un système de traitement des eaux usées à Labrecque” — tender scope, street work, pumping stations, mayor’s comments and funding timeline.
- Radio-Canada (ici.radio-canada.ca): “Eaux usées : le projet de plus de 30 M$ se concrétise à Labrecque” — 35-year history, 254 affected residences, council resolution of November 2, 2028 in-service target, and mayor’s interview.
- Public notice on wastewater work published by the Municipality of Labrecque (website and Facebook page), as cited by Le Lac-St-Jean.