Luxembourg Hospital Projects: €790M HRS, €683M CHL Overrun, Südspidol Delayed, Steinfort Scrapped

  • Kirchberg extension at HRS: €790 million in public funds, construction starts 2028, runs to 2039.
  • CHL new building: budget revised to €683 million, at least 5% overrun reported, completion July 2029.
  • Südspidol at Esch: €628 million allocated, financial questions unresolved, opening pushed to 2033–2034.
  • Steinfort project scrapped in current form; communes cannot bear financial burden, minister says.

The CHL project's revised envelope stands at €683 million, of which nearly €123 million has been paid to date.

The Hôpitaux Robert-Schuman (HRS) Kirchberg extension is among the largest projects.

The state’s share for new construction and extensions is estimated at €469 million, with another €323 million for modernizing existing buildings, a representative of the ministry of Health explained to the Health and Budget Control Commission. A 20-story hospital tower is planned. Work is set to begin in 2028 and proceed in phases until 2039, with modernization continuing to 2040.

CHL reports cost overrun

The Centre hospitalier de Luxembourg (CHL) has notified the ministry of a cost overrun of at least 5% on its new building, before contingency reserves are applied.

Twelve project modifications, estimated at €14 million, have been submitted, covering power supply and technical installations. About a quarter of the work is complete. The 476-bed building is due for completion in July 2029.

Südspidol financing still open

Some €628 million in public funds are earmarked for the Südspidol of the Centre hospitalier Emile Mayrisch (CHEM). During project review, 102 additional plan changes costing €54.2 million received preliminary approval. Doubts remain whether the current envelope can cover costs. Martine Deprez said the 2018 financing law must be adapted again.

“On the technical level, the file presents well, but financial questions remain unresolved,” Deprez said. Construction is slated to start in early 2029 for commissioning in late 2033; Deprez mentioned a horizon around 2034. The hospital was originally set to open in 2022.

Steinfort plan abandoned

The new building planned for the Hôpital intercommunal de Steinfort — 40 geriatric rehabilitation beds and 120 nursing beds — will not be realized as designed. The minister confirmed the change in response to a question from Dan Biancalana. The willingness to continue operating the nursing facility is no longer there, and the communes face financial difficulties.

“In the long term, the communes will no longer be able to bear the financial consequences of the project,” Deprez said. The option of offering only hospital activities in the existing building is under discussion but remains “at the discussion stage.” Legal clarification is needed on whether the commune syndicate will redefine its mission or transfer activities to another operator.

New clinics planned in Ettelbruck, Wiltz, Niederkorn and Eich

Additional investments include a new rehabilitation clinic at the Centre hospitalier neuro-psychiatrique (CHNP) in Ettelbruck, due in 2037; a medical center in Wiltz with polyclinic, outpatient surgery and imaging by 2031; an outpatient surgery building in Niederkorn, later to become a proximity clinic alongside Südspidol; and modernization of the Clinique d’Eich by 2031, focusing on orthopedics and sports medicine, according to Virgule.

The outpatient center “The Rock,” planned by HRS at Cloche d’Or, was not listed among the construction projects presented.

In response to Liz Braz, Deprez said the project has not yet been reviewed by the Permanent Hospital Sector Commission (CPH), though the file has been submitted.

Unlike classic hospital construction, no direct construction financing from the Fonds pour le financement des infrastructures hospitalières is planned. “Financing must rather go through operating lump sums calculated according to the number of patient contacts, as is already the case for other hospital sites,” Deprez said.