The Maharashtra Forest Department has issued a show-cause notice to Adani Green Energy Limited (AGEL) and ordered an immediate halt to construction at its 1,500 MW Tarali pumped storage project in Satara, following allegations that the company drastically understated project costs to reduce environmental obligations.
Affidavit Shows Massive Reduction in Estimated Project Costs
The controversy centers on a revision of the project’s estimated cost in a notarized affidavit submitted to the state forest department on September 8, 2026. While the Union Ministry of Environment, Forest and Climate Change (MoEF&CC) recorded the project cost at Rs 5,675 crore in its February 11, 2025, environmental clearance, the company’s affidavit listed the cost at Rs 56.75 crore, a 99 per cent reduction.
Critics, including Satara honorary wildlife warden Rohan Bhate, have argued that this reduction effectively lowered the company’s required conservation contribution. Bhate filed a complaint on October 30 through the Prime Minister’s grievance portal and the state government’s Aaple Sarkar platform, alleging that the project valuation had been shown at only a fraction of its actual cost to reduce environmental compensation liabilities.
Congress general secretary in-charge communications Jairam Ramesh described the cost revision as “unbelievable” and an example of what he termed the “Modani” conglomerate being “able to get away with.”

Company Response to Allegations
AGEL has rejected the claims, stating that the lower figure was provided solely for the purpose of an online proposal regarding site investigation and survey activities. The company maintains that the State Board for Wildlife (SBWL) considered the total project cost to be Rs 5,675 crore.
“The allegation that the company sought to revise project costs downwards to diminish statutory obligations is completely misleading,” a company spokesperson said.
“Since site investigation costs are around 1 per cent of project costs, therefore clarification of the project Rs 56.75 crore representing solely the site investigations and survey costs, for the online proposal was provided,” the spokesperson added. The company further said that the allegation that the revision was intended to lower conservation costs is “false.”
According to AGEL, the Tarali project is situated entirely on private, non-forest land in Patan taluka across the villages of Nivade, Tondoshi, Kalambe, and Jalu.
Forest Department Investigates Revised Costs as Protests Intensify
Principal Chief Conservator of Forests (Wildlife) M. Srinivas Reddy confirmed that the department has not accepted the revised estimate and is awaiting further documentation from the company. While the department had previously received a payment of Rs 56.75 lakh—representing 1 per cent of the revised cost—Reddy indicated that the department remains in a state of inquiry.
Local opposition has intensified, with hundreds of farmers, environmentalists, and activists protesting at the site. On Sunday, actor Sayaji Shinde and Vivekananda Patil visited the location to assess alleged damage to natural resources and filed a police complaint against the Adani Group.

Protesters fear that the project, which involves channeling water through tunnels before pumping it back to the reservoir, could cause irreversible ecological damage and lead to water shortages for local sugar cane and grape cultivation.
The Range Forest Officer of Patan issued a show-cause notice to the project authorities, demanding a written explanation within three days regarding the commencement of construction without mandatory clearance from the National Board for Wildlife (NBWL).
The notice seeks clarity on the authority under which construction began and requests copies of tree-felling permissions and other statutory approvals. The department has directed the project to stop all work immediately, warning that failure to comply could invite strict legal and penal action under forest laws.