Minister: Eskom Finishes Public Consultation for 5,200 MW Nuclear Plant

Eskom has finished preliminary public consultations for a nuclear power station of up to 5,200 MW at Thyspunt, near St Francis Bay in the Eastern Cape, moving the project to a detailed environmental impact assessment phase.

The Final Scoping Report was submitted to the Department of Forestry, Fisheries and the Environment on 6 July 2026, Kgosientsho Ramokgopa confirmed in response to a parliamentary question from MP Edwin Baptie. “The environmental impact assessment and the nuclear regulatory process, which are being conducted in parallel, have not been concluded,” he said.

Technology choice still open

Eskom has not selected a reactor supplier or finalised the technology. The environmental application uses a technology-neutral Plant Parameter Envelope to assess impacts for a station of up to 5,200 MW and associated infrastructure.

“The environmental application is based on a technology-neutral Plant Parameter Envelope that defines the parameters within which the environmental impacts can be assessed,” the minister said. “The application provides for a nuclear power station with a total generating capacity of up to 5,200 MW and associated infrastructure.”

Scale dwarfs existing fleet

The proposed capacity is more than double the 1,940 MW nameplate capacity of Koeberg in the Western Cape, South Africa’s only operating nuclear plant. Koeberg’s two units, which entered commercial service in 1984 and 1985, have received 20-year licence extensions and now generate about 5% of the country’s electricity, World Nuclear News reported.

(Image: South African Ministry of Energy)
Photo: World Nuclear News

Site selection and next steps

Thyspunt was chosen over alternatives such as Bantamsklip after preliminary investigations highlighted existing electrical infrastructure, proximity to wind farms, and Eskom land ownership. An Environmental Scoping Report found no environmental constraints that could not be mitigated. The next phase will update baseline data and examine transport networks, traffic, municipal services and the capacity of local, provincial and national authorities to support the development.

Heritage and community concerns

St Francis Bay, known as “Little Venice” for its whitewashed houses, black thatched roofs and extensive canal network developed from the 1950s, was declared a Grade I Cultural Landscape in January 2025. Residents and the South African Heritage Resources Agency have raised concerns about the project’s impact on the area’s heritage character.

Cost, funding and timeline

Ramokgopa could not provide a cost estimate, saying it depends on the reactor technology selected. Funding options include private-sector participation, public-private partnerships and project finance.

The minister aims for a final determination by the end of April 2027, after which procurement would begin, with the capacity scheduled to be on stream by 2039 under the 2025 Integrated Resource Plan, World Nuclear News reported. The department is preparing a proposed determination for public participation, with publication serving as the statutory trigger for procurement, Ramokgopa said.

Demand projections questioned

Analysts differ on the need for the new capacity. Matthew Cruise of Jaltech argued the 10GW ambition appears driven by vendor-country advice rather than system needs, while Tshepo Kgadima said the debate should focus on long-term energy security and reversing deindustrialisation. “Net electricity generation today is about 225 terawatt hours, roughly the same as it was 20 years ago in 2005,” he said. “My concern is how much capital is committed upfront when the first electrons to flow from Nuclear are about a decade away,” he said.

“Financial interest builds up during construction, and delays leave consumers paying higher tariffs or taxpayers covering guarantees.” “The real question is not whether South Africa needs nuclear power and the capacity thereof but rather whether the Minister has any comprehension of the geostrategic and geoeconomic implications of energy and specifically electricity for a developing country that has suffered years of deindustrialisation,” Kgadima said.

South Africa lacks recent nuclear construction experience

Ramokgopa acknowledged a key risk: South Africa has not built a nuclear plant in roughly 50 years. “At Koeberg, they know how to run an already-built power station,” he said. “The inherent risk is we don’t have people who have built nuclear power stations before.”

The South African Nuclear Energy Corporation (Necsa) welcomed the ministerial determination and is advancing efforts to re-establish front-end fuel-cycle capabilities, including uranium conversion, enrichment and fuel fabrication, World Nuclear News reported.

GroundUp reported on 13 April 2026 that a draft Environmental Scoping Report recommended Thyspunt over Bantamsklip, citing clear spatial, technical and infrastructure advantages such as Eskom land ownership and appropriate zoning within planning frameworks.

The document found Thyspunt’s reasonable proximity to existing transmission infrastructure and load centres reduces the need for extensive new powerlines and limits further land acquisition, whereas Bantamsklip is in a very remote location with few large distribution lines nearby.

The same report noted that rapid wind farm development beyond Thyspunt’s boundaries has already created a large network of new powerlines, giving the site better grid access than its rival.

The department is preparing a proposed determination for public participation, with publication serving as the statutory trigger for procurement, Ramokgopa said.