Missouri utility regulators held a sparsely attended public hearing last week on Ameren Missouri’s proposal to build a 2,100-megawatt natural gas plant in West Alton, a project critics argue could leave residential ratepayers exposed if data center demand falls short of projections.
The Missouri Public Service Commission hearing drew only three public testifiers after more than an hour of questions and answers, according to STLPR. The plant, intended to eventually replace the Sioux coal facility, would be one of Ameren’s largest in the state. The utility aims to break ground next year and begin commercial operation by 2031.
At issue is a dramatic divergence in demand forecasts. Ameren’s 20-year plan projects energy demand from large-load customers — primarily data centers — will jump 20% to 5 gigawatts by 2035, roughly half of the utility’s current 10-gigawatt supply. Residential and small-business demand is projected to grow just 1.2%.
“Our belief is that, based on the evidence available, the primary driver behind this is the increase in large load customers – primarily data centers – coming to the state,” said John Clizer, senior counsel for the Missouri Office of Public Counsel, the state agency representing utility customers.
Ameren Missouri’s Rob Dixon acknowledged rising demand is one factor but not the only one. “At the end of the day, people want the lights to work when they flip that switch, and that’s really what our most important priority is here,” Dixon said. He said the plant provides 24/7 generation as older facilities retire and cited 1,000 construction jobs and 45 permanent positions.
Ameren’s own project materials state that “large energy users must pay their fair share” and that state law and its “Powering Missouri Growth Plan” ensure existing customers will not pay costs created by data centers. The utility also says building adjacent to the existing Sioux Energy Center reduces construction and connection costs, and that paying some construction costs upfront lowers long-term financing expenses.
Critics warn the data center boom may not materialize as projected. Retired Boeing engineer Tom Golab testified that locking in a decades-long project lacks flexibility. “A technology project with this long time horizon benefits greatly from flexibility, which this project doesn’t have a lot of,” Golab said.
“Flexibility includes responsiveness to both risks and opportunities.” He noted rapid changes in AI power needs or the rise of regional hubs could mute demand, while advancing energy technology could yield cheaper alternatives.
Those concerns echo broader market signals. Heatmap News reported $260 billion in canceled data center projects this year alone. The Center for Public Enterprise found uncertain revenue and financing underpin the boom, warning a bust could be economically devastating. Tech Policy Press reported data centers are following a historical pattern of bubbles seen in railroads and internet infrastructure.
The Missouri Public Service Commission, led by Chairman Kayla Hahn and commissioners Maida J. Coleman, Glen Kolkmeyer, and John P. Mitchell as of 2025, holds statutory authority to review and approve project costs through a public process before they can be included in rates.
This gatekeeping power allows the commission to scrutinize Ameren’s generation plan and reject or modify cost recovery if projected data center demand fails to materialize, ensuring residential customers are not subsidizing stranded assets.
In 2025, the commission’s regulatory scope expanded when Governor Mike Kehoe signed a law restoring construction work in progress charges and adding tariffs, to be determined by the PSC, on users requiring 100MW or more of energy.
Dixon said Ameren plans for a range of macroeconomic scenarios and operates at a middle ground, adjusting as real commitments develop. The commission must review and approve project costs through a public process before they can be included in rates.