More Gas Storage Is at Risk. What’s the Government Plan for Secure Supplies? – The Guardian

SSE (LON: SSE) said on Wednesday it will begin closing its Atwick gas storage site in East Yorkshire in summer 2027 unless the government intervenes — pulling roughly 10% of Britain’s storage capacity off the market in the same week the National Energy System Operator repeated its warning that the country’s gas supply security is at risk.

The announcement, made alongside half-year results, lands months after Centrica (LON: CNA) set a spring 2027 closure for Rough, the country’s largest storage facility, The Guardian reported.

Together, the two sites account for the bulk of Great Britain’s storage buffer, and both owners are waiting on the same thing: a commercial framework that does not yet exist. The government launched a consultation on long-term gas supply in November 2025 and has still not published its full response, according to Reuters.

The stakes before April 2027

  • Atwick holds about 309 million cubic metres of gas — roughly 1.5 days of Great Britain’s demand, The Guardian estimated. Rough holds about 54 billion cubic feet, around half of national storage capacity, and Centrica says a fully stocked system covers about 12 days of demand against about six without it.
  • Neso’s updated assessment, published Wednesday, states the risk identified in 2025 “remains” and that an “enduring solution” is still needed; under a slow decarbonisation pathway, the UK fails resilience tests for winter 2036.
  • Centrica has fixed Rough’s consent expiry at 30 April 2027, giving ministers a hard deadline to act or lose the option entirely.

Atwick joins Rough on the closure path

SSE broke the news with its results for the six months ended 30 September, warning that without government intervention the facility would move into a multi-year programme of rewatering — pumping water back into the underground caverns to displace the gas — and then decommissioning, the Yorkshire Post reported. Any remaining gas would be sold, according to Reuters.

“Favourable spreads are not emerging to support the ongoing commercial operation of Atwick.”

the company told investors, while insisting that “the strategic importance of fast-cycle gas storage assets to the UK’s energy system remains unchanged.” The site near Hornsea consists of eight caverns, has operated since 1979 and has been owned by SSE since September 2002.

Here is the capacity at risk: Reuters puts Atwick at nearly 10% of the UK total, while The Guardian calculates it at about 20% of Great Britain's onshore storage — the two figures differ because Rough sits offshore. Either way, it is the second storage site on a closure path within months.

More Gas Storage Is at Risk. What’s the Government Plan for Secure Supplies? - The Guardian
Photo: Energy Live News

But the balance sheet tells a different story about the company itself. SSE posted adjusted pre-tax profits of £999.7m for the half-year, up from £523.7m a year earlier, and delivered a record £2.6bn of capital investment, around 70% of it into regulated electricity networks, the Yorkshire Post reported. The group is not in distress; it is reallocating capital.

“A year ago, we set out our five-year £33bn investment plan to transform SSE for growth. Today, from the Highlands to the North Sea, that plan is translating into infrastructure on the ground, supporting lower bills and providing greater energy security.”

said Martin Pibworth, chief executive of SSE, in the results statement. The company is also commissioning Dogger Bank wind farm off the Yorkshire coast, with 52 turbines installed on Dogger Bank B and cabling work on Dogger Bank C nearing completion.

The risk Neso flagged twice

On Wednesday, the same day as SSE’s announcement, the National Energy System Operator published its latest gas supply security assessment. “Our updated analysis shows that the risk identified in our 2025 assessment remains, and that there is an ongoing need for an enduring solution to secure future gas supply,” the report said, as quoted by The Guardian.

The headline finding is reassuring on the surface: per Energy Live News, Neso expects supplies to reach almost all levels of demand in the winters of 2031/32 and 2036/37, provided every source stays available. The catch sits underneath.

The likelihood of negative gas supply margins — supply failing to meet demand — rises materially if the largest single piece of infrastructure, such as an import terminal, is lost, and the risk is “materially higher under the slowest decarbonisation pathway,” Energy Voice reported. On that slower path, the UK only narrowly passes resilience tests for winter 2031 and fails them for winter 2036.

The assessment also assumes domestic production keeps shrinking. It uses the North Sea Transition Authority’s projection of a 78% drop in gas availability from the UK Continental Shelf between 2025 and 2035, according to Energy Voice. Neso found no scenario in which UK production, biomethane and Norwegian imports alone meet demand.

“Gas security remains fundamental to the resilience of Great Britain’s whole energy system.”

said Dr Deborah Petterson, Director of Whole Energy System Resilience at Neso, in comments carried by Energy Live News.

Why the summer-winter spread collapsed

Storage makes money on a simple trade: buy gas in summer when demand and prices are lower, hold it, sell into winter peaks. That spread has disappeared. According to The Guardian, prices inflated by the Iran conflict and the effective closure of the Strait of Hormuz have made filling stores over the summer unprofitable, meaning European facilities head into winter with inventories at their lowest point in over ten years.

SSE’s own language matches that diagnosis: challenging market dynamics across HY27 have “constrained the value” of the site, despite current commodity prices. Both operators are acting commercially rationally — which is precisely the problem, because what is rational for an individual firm strips resilience from the system as a whole.

The cost is already reaching households. Cornwall Insight forecasts a 26% rise in the typical annual gas and electricity bill in January, to £2,166, according to a report carried by Traders Union.

A consultation with no answer

The government’s position has not moved since the summer. “We recently confirmed plans to explore commercial support for storage and the wider sector, to help protect our gas security,” the energy department said on Wednesday. “We will set out proposals in due course.” A consultation launched in November 2025 on long-term gas supply remains unanswered in full, Reuters noted.

Meanwhile the system has run close to the edge. The Guardian reports that gas security for this winter already required an eleventh-hour deal with Belgium to avert a planned cut in interconnector capacity. And the timing pressure is asymmetric: Atwick could probably be reopened after closure, but that is less true of Rough, whose consent expires on a fixed date.

There is a new note of confidence on the supply side. Energy minister Michael Shanks marked the first output from the Jackdaw gasfield off Aberdeen this week, declaring it “will increase domestic production and further boost our energy security during the transition to electrification and decarbonisation.”

The Guardian, which covered the moment, noted the minister appeared to be “almost dancing a jig of delight” — and asked why approval took a year of ministerial agonising if the security case was so clear.

The negotiating clock runs one way

Site Owner Published capacity Share of GB storage Demand cover
Atwick SSE 309 million cubic metres Nearly 10% of UK total (Reuters); ~20% of GB onshore (The Guardian) ~1.5 days of GB gas usage (The Guardian)
Rough Centrica 54 billion cubic feet (~1,529 million cubic metres) About half of Britain’s storage capacity (Centrica, via Streamline Feed) ~12 days fully stocked vs ~6 without (Centrica, via Streamline Feed)

Delay has already shifted bargaining power toward the operators, The Guardian's analysis argues: if ministers ultimately need a deal, they will be negotiating with firms whose assets are days from becoming uneconomic to keep open. Unite has called on the government and Centrica to collaborate over Rough, which is set to shut in April 2027.

The open question is whether the government’s “due course” arrives before the options narrow. Rough’s consent date is fixed at 30 April 2027.

Disclaimer: The information provided in this article is for educational and informational purposes only and does not constitute financial advice.

Photo of author

Newsroom

Newsroom at Archyde.

Study: Children With Eczema Have Higher Odds of Sleep Disturbance

ICJ to Rule on Myanmar Genocide; Fears Rise of US Sanctions on Judges