Electricity demand reached a record 4,195 billion kilowatt-hours in 2025, yet grid reliability is failing to keep pace. As data centers drive load growth, supply constraints have forced power auctions to their price caps.
In Southern California, the 2013 retirement of the San Onofre Nuclear Generating Station (SONGS) forced a transition to natural gas, increasing generation costs by $350 million in 2012 alone, according to California Globe. The loss of that 8% of state electricity supply squeezed transmission, a structural deficit that persists as demand hits new peaks.
- Auction Volatility: The PJM Interconnection 2028/29 capacity auction cleared at its $325 per megawatt-day cap, yet still finished 6,831 MW short of reliability requirements.
- Retail Price Inflation: U.S. residential electricity prices averaged 18.16 cents per kilowatt-hour in August, a 3.4% increase year-over-year, with California consumers paying a premium 64% above the national average.
- Regulatory Friction: Despite the Nuclear Regulatory Commission (NRC) relicensing the Diablo Canyon units through 2044 and 2045 on April 2, 2026, state law mandates a 2030 shutdown for a facility providing nearly 20% of California’s clean energy.
The financial impact of these decisions is visible in the Energy Information Administration data, which shows a consistent climb in residential rates. While state officials, including the California Legislative Analyst’s Office, point to wildfire mitigation and climate program costs as primary drivers, the loss of firm, baseload nuclear capacity has removed a critical hedge against price volatility.
| Metric | Value | Context |
|---|---|---|
| U.S. 2025 Consumption | 4,195 Billion kWh | All-time record |
| PJM 2028/29 Shortfall | 6,831 MW | 14.7% reserve margin vs 20% target |
| National Avg Price (Aug) | 18.16 cents/kWh | 3.4% increase YoY |
| California Avg Price | 29.75 cents/kWh | ~64% higher than national avg |
Critics of nuclear expansion point to the fiscal performance of Southern Company and its Vogtle units, which were completed seven years behind schedule and $17 billion over budget. The financial burden shifted to Georgia ratepayers, who are covering $7.56 billion of the cost overruns. This experience illustrates the difficulty of scaling complex infrastructure in a regulatory environment that prioritizes litigation over standardized, repeatable designs.
According to the Energy Information Administration, the U.S. nuclear fleet achieved a 91% capacity factor in 2025. New fuel technologies, such as TRISO particles, offer enhanced safety profiles that the Department of Energy describes as resistant to melting under design-basis conditions, potentially allowing for smaller emergency planning zones.
The Berkeley Lab reports that interconnection queues contain 2,061 gigawatts of proposed projects, yet only 13% of projects requested between 2000 and 2020 have reached commercial operation. The median wait time for a project to reach operation has surged to 61 months, up from 22 months in 2008. This delay effectively prevents supply from responding to the rapid load growth fueled by artificial intelligence and data center expansion.
“The first lesson of economics is scarcity,” as Thomas Sowell noted, a sentiment currently reflected in the PJM auction results where, absent price caps, clearing prices would have exceeded $550 per megawatt-day.
For instance, the Mojave Desert’s Ivanpah solar-thermal plant, which operates on a $1.6 billion federal loan guarantee, continues to function despite efforts by both the Biden and Trump administrations to shutter the facility. The California Public Utilities Commission rejected PG&E plans to close the plant, citing an urgent need for existing capacity.