Tenaris has secured a strategic victory in the race to supply infrastructure for Argentina’s burgeoning liquefied natural gas (LNG) sector, winning the bid to manufacture steel pipes for the Argentina LNG project.
The deal marks an industrial comeback for the Techint Group, which will produce the 24-inch pipes at its Tenaris SIAT plant in Valentín Alsina, Buenos Aires province.
The announcement came from YPF president Horacio Marín, who revealed the results during an appearance on the Neura program. Marín described the procurement process as a highly competitive “Japanese-style” reverse auction, where participating companies lowered their prices in real-time until a single winner remained. “It was an inverse, it was very competitive and Tenaris won,” Marín told the program, as reported by La Nación.
Industrial Redemption in the Conurbano
For the company led by Paolo Rocca, the win provides a critical boost to its local manufacturing footprint. Less than a year ago, the Valentín Alsina plant faced a public setback when it lost a major tender for the Southern Energy (SESA) gas pipeline to India’s Welspun. That loss, valued at US$203 million, showed the intense pressure Tenaris faced from international competitors on pricing, Perfil reported.

The new contract covers the 24-inch pipeline designed to transport liquids, a component requiring approximately 100,000 tons of steel. While Tenaris emerged as the winner for this segment, the project’s larger 48-inch gas pipeline—the largest diameter in the country’s history—will be supplied by foreign firms.
The Spanish company Grupo Cuñado, utilizing Indian-sourced steel, will provide 200 kilometers of pipe, while the Greek firm CPW will supply the remaining 300 kilometers. Marín said that Tenaris did not participate in the bidding for the 48-inch section because the company lacked the specific manufacturing capacity for that diameter in Argentina.
Pipeline Procurement Marks Major Milestone
The pipe procurement, totaling roughly US$2 billion, represents a pivotal milestone for the Argentina LNG project, a massive US$29 billion venture backed by YPF, the Italian energy giant Eni, and XRG, the investment arm of the Abu Dhabi National Oil Company (Adnoc). This infrastructure is essential for connecting the Vaca Muerta shale play to the coast of Río Negro.
The construction of the 526-kilometer pipeline network is being handled by a consortium consisting of the American firm Pumpco, Italy’s Bonatti, and the Argentine company Contreras Hermanos. The project’s scale is immense; during a recent public hearing in Sierra Grande, YPF representatives estimated that the construction phase, scheduled between 2027 and 2030, would create 20,000 direct and indirect jobs, with peak employment potentially reaching 40,000 workers, Diario Río Negro reported.

With the suppliers now finalized, the project is moving toward the Final Investment Decision (FID), which is slated for November 26 under the regulatory stability framework provided by the RIGI (Régimen de Incentivo para Grandes Inversiones).
The infrastructure is designed to feed two floating liquefaction units in Sierra Grande, capable of exporting 12 million tons of LNG annually, potentially generating between US$10 billion and US$12 billion in yearly foreign exchange earnings for the country.
Local Development and Environmental Oversight Drive the Project
The significance of the project extends beyond energy exports, as provincial authorities view it as a catalyst for local development. Río Negro Governor Alberto Weretilneck emphasized the project, stating, "We are going to be part of this history as Río Negro deserves," during a recent official address.
The provincial government has implemented the Ley de Empleo Rionegrino, which mandates that 80% of the workforce for such projects must be local residents.

Environmental compliance has also been a focal point of the planning process. A recent public hearing in Sierra Grande, which spanned 13 hours of debate, reviewed the environmental and social impact studies conducted by the consultancy Serman & Asociados.
According to LMNeuquen, the study assessed the impact of the pipeline route, which includes a complex crossing of the Limay River, and established that the pipeline’s presence would be compatible with existing land uses like livestock grazing, provided that no excavation occurs within the designated right-of-way.
While the technical and procurement hurdles are largely being cleared, the industry remains focused on the upcoming FID. The project aims to have the first liquefaction vessel operational by 2030, with a second unit expected to join the line in 2031.
For now, the successful tender by Tenaris serves as a signal of both the project’s momentum and the competitive nature of the infrastructure contracts currently being awarded in the Argentine energy sector.