The Saint-Nazaire wind farm disconnected from the network for several hours

MOBILISATION

The two cables that connect this highly symbolic installation within the framework of the development of renewable energies, have been disconnected, an act claimed by the CGT RTE

  • On Thursday, the Saint-Nazaire offshore wind farm was disconnected from the electricity grid for several hours.
  • The perpetrators of the action apparently broke into the Prinquiau substation, which links the maritime network and the land network, according to RTE, which filed a complaint.

The mobilization against pension reform continues in particular in the energy sector. Here is a new demonstration: Thursday, the Saint-Nazaire offshore wind farm (Loire Atlantique) was disconnected from the power grid for several hours, we learned from concordant sources. “The new offshore wind turbine platform in Saint-Nazaire was turned off for at least five hours,” said the CGT RTE, claiming other cut-off actions in France, particularly in the industrial zone of the plain of the Ain. “No compromise, no mediation, no bogus meeting, only one watchword: withdrawal! “, also indicated the CGT in his message.

“The Saint-Nazaire wind farm was disconnected from the electricity grid from 10:11 a.m. to 1:13 p.m. for the first link and until 3:52 p.m. for the second,” said the management of the high and very high voltage line manager RTE. The two cables that connect this highly symbolic installation within the framework of the development of renewable energies in France, were therefore disconnected for three hours and five and a half hours, according to RTE, which confirmed that the energy produced by the wind turbines did not have no longer supplied the transmission network during this period.

RTE will file a complaint

The perpetrators of the action apparently broke into the Prinquiau substation, which links the maritime network and the land network, to disconnect the two lines, according to RTE, who announced his intention to file a complaint, as he does systematically, after this type of action. The offshore wind platform of Saint Nazaireinaugurated by Emmanuel Macron at the very beginning of autumn, is the very first offshore wind farm commissioned in France, 10 years after its award. Its 80 wind turbines must ensure the equivalent of the annual electricity consumption of 700,000 people.

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.