Transnet Clears 18 Priority Pharma Containers

Transnet cleared 18 of 41 priority pharmaceutical containers through Durban’s port by Monday, while 16 more await berthing nominations at the Durban Gateway Terminal and seven are expected to arrive by 2 December 2026.

Business Day reported the update from the state freight company, which is working with terminal operator Durban Gateway Terminal (DGT) to ease a backlog that has stretched vessel waiting times to 20 days.

The terminal handles 50% of the country’s container freight. It has been congested since ICTSI took over operations in January under a 25-year concession. Transnet retained a 50.001% stake after selling 49.999% to the Philippine operator for R10.5 billion in 2026.

Health director-general Thembisile Xulu told parliament last week that the list of medicines at risk of stockouts had more than doubled since May, reaching 184 items by 16 November. Business Day said delayed drugs include antibiotics and treatments for high cholesterol, high blood pressure and stomach ulcers.

Blame Over Equipment and Software

ICTSI attributed the backlog to “the poor and unsafe condition of equipment at the facility, owing to years of underinvestment and inadequate maintenance,” the company said in a statement cited by Moneyweb. The operator also said its new Navis N4 software was “running smoothly” and assisting operational recovery.

Transnet pushed back, saying ICTSI’s characterisation of the terminal as a failed operation was “inconsistent with the evidence”, while welcoming the investment and expertise ICTSI brought. Moneyweb reported Transnet’s response on Saturday.

Transport Minister Barbara Creecy criticised the timing of the system cutover. The Transnet National Ports Authority gave DGT three months to improve performance or risk losing its operating licence. EWN reported the ultimatum.

Durban port crisis and debt hurdles test SA’s private rail overhaul
Photo: Daily Maverick

Creecy also acknowledged the equipment needed investment but faulted DGT for introducing a new operating system just before the peak festive season. BusinessTech reported from a Bloomberg interview.

Retail and Agriculture Leaders Warn of Costly Delays

Mr Price CEO Mark Blair questioned why terminal software was changed in August, so close to the Christmas trading peak. “We planned to do these things well away from peak, because we all know that they’re never problem-free,” Blair told Moneyweb.

The retailer, which also sells homeware, uses imported fabric and expects stock to reach stores by 16 December. Metair CEO Paul O’Flaherty earlier told Moneyweb he could not see an end to the crisis, calling the delays highly costly.

AgriSA chief operating officer Jolanda Andrag said Durban handled nearly 88% of South Africa’s wheat imports in the 2025/26 marketing season and 43% of citrus pallets exported through five southern African ports in 2025. Farmer’s Weekly SA reported that citrus growers missed selling windows during the 2026 backlog.

The port also handled all seaborne whole-maize exports recorded by SAGIS in 2025/26, amounting to 364,826 tonnes.

Rail Shift Stalls as Trucks Clog Highways

The congestion has spilled onto the N3, N2 and N11 routes. KwaZulu-Natal MEC for Transport Siboniso Duma said on 19 November that the pressure to move freight quickly creates a high-risk environment driving truck accidents. Arrive Alive reported.

Shipping containers at the port
Photo: Farmer's Weekly SA

Transnet’s recovery plan includes moving more containers by rail to Gauteng. The share of national freight on rail has slipped to below 15% in 2025 from 22% in the mid-2010s, according to Trade and Industrial Policy Strategies cited by Daily Maverick. That “contradicts the long-standing national policy goal of shifting from road to rail”, the article said.

Transnet Rail Infrastructure Manager (Trim) CEO Moshe Motlohi said his team is working towards the government’s pledge of moving 250 million tonnes by rail, up from 168 million tonnes at the last financial year-end. “The railway needs trucks because we cannot get door-to-door, but the trucks need us to carry more cargo, and that is going to lower the cost of doing business,” Motlohi told Daily Maverick.

New rubber-tyred gantry cranes are due in December and March 2028.

Automotive Industry Warns of Competitiveness Risks

Ford Motor Co. South Africa president Neale Hill said ongoing delays and uncertainty at the port increase logistics costs and undermine the predictability and competitiveness the automotive industry needs to serve domestic and export markets effectively. BusinessTech reported.

Hill encouraged the relevant parties to resolve the current uncertainty as a matter of urgency and provide clarity on the path forward.

ICTSI
Photo: Arrive Alive

The Democratic Alliance’s KwaZulu-Natal health spokesperson Dr Imran Keeka warned that delays affecting approximately 30 ships carrying medicines and pharmaceutical supplies at Durban Port could further worsen shortages at public healthcare facilities. The Citizen reported.

Keeka said oversight inspections at two hospitals had identified more than 100 medicines out of stock. He warned that a situation where hospitals only begin seeing meaningful replenishment in March 2027 cannot be afforded.

Emergency Rail and Berth Capacity Deployed

Transnet Freight Rail is making trains available to enable evacuation of import containers destined for Gauteng. Transnet National Ports Authority has offered additional berthing capacity. Daily Maverick reported.

Transnet is also coordinating with shipping lines on alternative berthing options at Durban Container Terminal Pier 1, Maydon Wharf and Ngqura Container Terminal, according to The South African.

Transnet Considers Alternative Berths to Ease Durban Congestion

Transnet said “a proposal to berth and discharge urgently needed containers at other terminals is being considered, to prevent queuing in Durban. This will be finalised before the vessels arrive,” the company said on 18 November. Options include Durban Container Terminal Pier 1, Maydon Wharf and Ngqura Container Terminal.

TNPA separately opened an expression of interest for private participation in existing capacity at the Island View precinct, which handles 74% of liquid bulk imports. It stressed it “should not be construed as an invitation for the development of new petroleum storage infrastructure.”

DGT said original equipment manufacturers are on site repairing existing machinery. First new equipment deliveries are expected by end of November and more in the first quarter of 2027. Freight News reported the timeline. The terminal is also implementing a new truck appointment system.