Driven by an explosive demand for artificial intelligence computing capacity, U.S. data center construction costs rose 13% in 2026, outpacing the global rate and climbing at roughly triple the ten-year average as developers competed for scarce powered land and skilled labor.
The acceleration of large-scale infrastructure projects this year outran the available supply of electrical grid connections and construction workers, pushing timelines and financial risk onto contractors, according to an annual index from project management firm Turner & Townsend.
While private companies ramped up digital real estate spending to an annual pace of roughly $85 billion by August—up 73% from a year earlier, as Quartz reported—the resulting bottlenecks forced construction expenses to more than double the worldwide pace.
AI Data Centers Cost 10% More to Build than Traditional Ones
The CNBC Property Play newsletter detailed that the project management firm’s index examined over 500 live or recently completed projects across 62 global markets alongside a survey of more than 400 industry experts. The findings show that facilities built specifically for artificial intelligence workloads cost approximately 10% more to construct than traditional data centers, driven by higher rack density requirements, liquid cooling systems, and compressed delivery schedules.
Regional variations in development expenses reflect deep disparities in local grid capacity and labor markets. Based on a typical 60-megawatt design benchmark, construction costs reached $15.01 per watt in Silicon Valley, whereas Dallas projects averaged $10.51 per watt, according to data highlighted by MLQ.ai. Nationally, the U.S. average settled at $12.08 per watt, while the most technologically advanced artificial intelligence sites ran between $14 and $16 per watt.
Power availability emerged as the primary operational hurdle for developers. Approximately 56% of survey respondents identified utility connections as a major obstacle to project delivery, with more than half reporting that obtaining power links takes between one and two years, and nearly a third noting wait times exceeding two years, as noted by International Business Times.

Labor constraints compounded these delays. Survey data revealed that 81% of industry leaders viewed skilled labor in their regions as moderately or highly constrained, particularly within mechanical, electrical, and plumbing trades. Only 26% of respondents in North America believed regional contractor capacity was sufficient to manage existing construction backlogs.
Contractors responded to compressed timelines by baking financial safeguards directly into their project bids. “More aggressive schedules tie to contractors in particular and subcontractors baking in more risk allowances in their pricing,” said Paul Barry, North America data center lead for Turner & Townsend.
“So whether that’s acceleration allowances, whether that’s more overtime and labor attraction allowances, even just higher fees for taking on the risk of delivering at a faster pace than what they would traditionally take on,” Barry told CNBC.
Over the long term, global capital spending on digital infrastructure is expected to grow substantially. A recent report from PwC forecasts that worldwide data center capital expenditures will climb from approximately $800 billion this year to $1.8 trillion annually by 2050, with the United States expected to capture nearly half of all global investment in artificial intelligence hardware and real estate.
Despite the acute cost pressures experienced in 2026, industry projections point toward a modest deceleration in price growth. Barry expects cost increases to moderate into a range of 6% to 10% over the next year, noting that a vast share of major developments are already underway or entering construction phases with risk allowances fully priced into their executed contracts.
“If this demand continues, then there’ll be more continued flow of project starts and so on, but I think we’ve hit a big surge in 2026, especially of new big major projects that have been procured,” Barry told CNBC.
Operating as a multinational professional services firm, Turner & Townsend traces its origins to a quantity surveying partnership established in 1946. Over the following decades, the consultancy expanded globally and grew into one of the world’s largest construction consultancies, eventually opening its first international office in Johannesburg in 1982.
The firm is known for providing programme management, project management, and cost management services across property, infrastructure, and natural resources sectors. Its notable projects include project managing the construction of The Shard, the tallest building in London at the time of its completion.
Disclaimer: The information provided in this article is for educational and informational purposes only and does not constitute financial advice.