Work Begins on Tuas Port Phase 2 to Expand Singapore’s Maritime Capacity From 2028

“Maritime connectivity is our lifeblood,” said Transport Minister Jeffrey Siow at Friday’s groundbreaking for Tuas Port Phase 2 in Singapore.

The second and largest of the port’s four development phases will begin operations from 2028, with all 21 deepwater berths expected to be running by the mid-2030s, PSA Singapore said on Friday (Nov 20).

The phase spans nearly 400 hectares of reclaimed land — roughly 560 football fields — with a water depth of 23 metres and 8.6 kilometres of wharf, the longest of the four phases. It is designed to take the world’s largest container vessels. Work on the phase, also known as Finger 3, began on Nov 20 on land reclaimed from open sea since March 2018.

When the full port is completed in the 2040s, all of Singapore’s container operations will consolidate at Tuas, making it the world’s largest fully automated port: 66 mega berths and capacity of 65 million twenty-foot equivalent units a year. The reclaimed site is close to the size of Clementi Town.

These are the numbers behind the stakes. Tuas Port opened in 2022, has since handled 25 million TEUs, and now operates 15 berths on track to reach 18 by 2027. Phase 2 alone adds 21 berths — more than doubling today’s operational count.

Work Begins on Tuas Port Phase 2 to Expand Singapore's Maritime Capacity From 2028
Photo: DredgeWire

The Bottom Line

  • Phase 2 is the largest of four phases: 21 berths, 23m draft, 8.6km of quay, operational from 2028.
  • Reclamation for the phase’s Northern Berths (Finger 3) finished on Nov 10, after more than 24 million man-hours and over 197 companies.
  • The Maritime Singapore Master Plan, focused on capacity, technology and talent, will be launched in April 2027.

What Siow, Ang and Voser each said

Siow framed the project as existential for a nation importing almost all of its food, energy and supplies by sea. “As a small island nation without any natural resources, maritime connectivity is our lifeblood,” he said. The seaport connects Singapore to more than 600 ports worldwide and supports more than 140,000 jobs.

He also set out the commercial ambition. “We want Singapore to be the port of choice for global shipping and a hub of flows where global maritime trade is managed and shaped,” Siow said. At the same event, he said Singapore wants to evolve “from being a hub of firms to a hub of flows,” anchoring more maritime headquarters in ship financing, insurance and data.

MPA chief executive Ang Wee Keong put a number on the labour involved. The Northern Berths project involved more than 24 million man-hours and over 197 companies, he said, and weathered pandemic-era work suspensions, manpower shortages and supply-chain disruptions.

“In breaking ground on Phase Two at Tuas Port, PSA was not simply adding capacity, but laying the foundations for a more integrated port ecosystem that delivers greater value for its customers, partners and the wider supply chain,” said Peter Voser, Group Chairman of PSA International. Group Chairman Peter Voser

Where the outlets differ on berth counts

MPA’s own chief executive said Phase 1 has 14 berths currently operational.

Work Begins on Tuas Port Phase 2 to Expand Singapore's Maritime Capacity From 2028
Photo: The Straits Times
Phase / milestone Berths Status
Phase 1 (operating) 15; 14 (per MPA’s Ang) Since 2022; 25 million TEUs handled
Phase 1 expansion 18 On track by 2027
Phase 2 / Finger 3 21 Operations from 2028; full by mid-2030s
Full port (2040s) 66 65 million TEU annual capacity

The technology bet under the concrete

Phase 2 is not only steel and landfill. PSA will scale up to around 1,000 next-generation Intelligent Guided Vehicles that calculate and optimise their own routes in real time, operating safely alongside manned vehicles. Around 30 IGVs are already being tested at Tuas. The new units are not bound to fixed routes, unlike earlier versions.

The phase also ties into the PSA Supply Chain Hub @ Tuas, which PSA says will let cargo owners store, process, consolidate and distribute goods quickly to regional markets. Siow argued shipping lines count on Singapore for fast turnaround or to make up for delays elsewhere along their routes.

A $20 billion bet on the 2040s

The full Tuas Port development covers more than 1,330 hectares and costs more than $20 billion. That is the context for Siow's timing: the MPA will unveil the Maritime Singapore Master Plan in April 2027, focused on expanding port and maritime ecosystem capacity, using technology and innovation, and investing in maritime talent.

Psa tuas port phase groundbreaking
Photo: AsiaOne

Engineering context: Phase 2 reclamation began in March 2018, and the wider works involve 227 massive caissons forming about 9.1km of seawall. MPA handed over the first completed reclaimed sections for berths B7 and B8 to PSA earlier this year. PSA is targeting 2028 for the first operational berth at Finger 3.

Siow closed the ceremony framing the horizon beyond the concrete. “In doing so, we are not just building a port just for the next decade — we are securing Maritime Singapore for generations to come,” he said.

Tuas Port’s story began in February 2015, when the Maritime and Port Authority of Singapore started reclamation works for Phase 1 — a project spanning 34 million man-hours with the support of over 450 companies. Its first two berths began operations in December 2021, ahead of the port’s official opening on 1 September 2022. When completed, the port will occupy about 1,337 hectares, roughly 3,300 football fields, with 66 berths spanning 26 kilometres.

PSA expects to move all operations at Tanjong Pagar, Keppel and Brani Terminals to Tuas Port by 2027, with Pasir Panjang Terminal to follow by the 2040s. PSA is also aiming for the port to reach net zero emissions by 2050, using electrified automated equipment and a smart grid management system.

Disclaimer: The information provided in this article is for educational and informational purposes only and does not constitute financial advice.

Photo of author

Newsroom

Newsroom at Archyde.

Hyundai Santa Fe Celebrates 25 Years in Europe: From First SUV to “Open for More” Flagship

PowerCompute Sells 267 BTC to Repay $22M Debt; Going-Concern Doubt Remains