Digging and filling nearly 2 million m3 of land at Long Thanh airport during Tet holiday | Society

Construction at night on the construction site of Long Thanh airport. (Photo: Cong Phong/VNA)

On January 26, the Long Thanh Airport Project Management Board said that in the 7 days of the 2023 Lunar New Year, the joint venture contractors nearly 2 million m3 of land has been dug and filled at Long Thanh airport.

To ensure the progress of Long Thanh airport, from January 20-26 (December 29 in the year of the Tiger to the end of January 5 in the year of the Rabbit), a consortium of five contractors mobilized nearly 600 excavators and trucks. bulldozers, rollers, graders, transport cars, water trucks and 650 engineers and workers organized 20 construction projects on the construction site of Long Thanh airport.

Tet holidays, construction work at Long Thanh airport only deployed during office hours, concentrated in the area later built runways, taxiways, aprons.

According to the leader of the Long Thanh Airport Project Management Board, most of the workers working at Long Thanh airport are from the northern and central provinces, according to the schedule from January 27 (ie the 6th of the Lunar New Year 2023). ) workers will return to the construction site.

However, due to many reasons, from January 31, all engineers and workers returned to full capacity, at that time construction at Long Thanh airport will take place simultaneously.

[Hơn 2.000 máy móc, nhân lực thi công xuyên Tết ở sân bay Long Thành]

To take advantage of the dry season, from February 2023, the consortium of contractors mobilized about 770 more machines and equipment (increasing the total number of machines at the construction site to more than 2,000 units) and 2,500 employees to deploy 44 construction tip, ensuring every day and night to excavate and backfill 500,000 m3 of soil.

In addition to speeding up the project, the investor of Long Thanh airport thoroughly understands to the contractors and supervision consultants the principle that quality must come first, not follow the schedule but neglect quality and must ensure labor safety and environmental sanitation during construction.

Long Thanh airport has an area of ​​5,000ha, designed capacity of 100 million passengers/year. This is a traffic project with the largest investment capital ever in our country, started in 2021, expected to be put into operation in 2025.

Up to this point, the airport has completed the pile foundation package for the passenger terminal, the contractors are focusing on leveling and drainage, and nearly 53 million m3 of land has been dug and filled.

Cong Phong (VNA/Vietnam+)