MRTA update work pink-yellow line Running for sure this year Let’s go to the provinces. Pak flag big cities – Post Today economic-business news

MRTA update work pink-yellow line Running for sure this year Continue to the provinces. Flag the big cities.

Date 05 Apr 2022 time 17:05

The Cabinet acknowledged the MRTA profit of 1.9 billion, indicating that the three train routes were completed earlier than planned. Until this year, the pink-yellow line is ready to serve. Proceed to the Phu Thon Line Phuket-Chiang Mai-Korat

Miss Traisulee Traisornkul, Deputy Spokesperson for the Prime Minister’s Office revealed that the meeting The Cabinet (Cabinet) acknowledges the operating results of the Mass Rapid Transit Authority of Thailand (MRTA) in fiscal year 2021 with a net profit of 1,927.83 million baht, with revenues of 16,018.27 million baht, a subsidy of 10,434.78 million baht and expenses. Paid a total of 14,090.44 million baht, able to disburse 99.99 percent of the investment budget.

In addition, there was revenue from continuing business from the MRT Chaloem Ratchamongkhon Line of 104.16 million baht, below the target of 33.48 million baht, and the Chalong Ratchatham Line of 24.26 million baht, below the target of 6.73 million baht, with a return on assets of 1.20% from the target. 0.85

Currently, there are 3 projects under construction, namely the Orange Line. During the Cultural Center of Thailand – Min Buri (Suwinthawong), the study and analysis of the project was completed. construction work The production and installation of electric train systems and operating work has progressed 89.70 percent, 0.44 percent faster than planned. It is expected to open for service in March 2025.

MRT Pink Line Project, Khae Rai – Min Buri Section construction work Production and installation of the electric train system and the operation work has progressed 90.70 percent, faster than the 1.74% plan, expected to open for service in September 2022, and the MRT Yellow Line Project, Lat Phrao-Samrong Section. construction work Production and installation of electric train systems and operating work has progressed 84.90 percent, faster than the 4.19 percent plan, expected to open in June 2022.

There are 2 projects currently under tendering, namely the Purple Line Project. During the Tao Poon – Rat Burana (Kanchanapisek Ring Road) land ownership work has progressed 37.75%, which is according to the plan. and the construction of civil works The production and installation of the electric train system and the operation of the train had a progression of 9.10 percent, slower than the plan by 0.73% because MRTA had announced the cancellation of the civil works tendering. to create greater public participation It is expected to open in December 2027.

MRT Orange Line Project: Bang Khun Non Section – Thailand Cultural Center Land ownership work progressed 17.80 percent, slower than planned by 0.20%. Production and installation of the electric train system and the operation of the train had a progress of 5%, which was in accordance with the plan. It is expected to open in September 2027.

As for the projects that are under study and analysis, there are 4 projects as follows: Phuket electric train project Expected to open for service in December 2026, the Chiang Mai Railway Project. It is expected to open in February. 2528, the electric train project in Nakhon Ratchasima It is expected to open for service in February 2028 and the Phitsanulok Electric Railway Project. It is expected to open for service in July 2028.

while the MRTA’s projects and plans in the future in the development of the mass transit system MRTA has prepared for the use of a common ticket system. The EMV contactless joint ticketing system will be officially available on the Chaloem Ratchamongkhon Line and Chalong Ratchatham Line by 2022.