A 51-million-euro cold storage warehouse holding 40,000 pallets opened in Argentan, France, on Thursday — and its Dutch owner already expects it to fill within a year.
NewCold built the 6,000-square-meter, 32-meter-tall facility to meet what it calls strong local demand for frozen food capacity, Radio France reported.
The building, formally an “entrepôt de stockage frigorifique,” is the company’s second on the Putanges industrial zone. NewCold, a Netherlands-based cold storage specialist, already operates an identical structure there, built in 2011.
Why spend €51 million twice in the same town? The driver, according to Radio France’s report on the inauguration, is the growth of Ysco, the ice cream manufacturer also based in Argentan, whose frozen production must be warehoused ahead of a short, intense selling season. Around that anchor customer, the broader regional market — prepared meals, fish, shrimp, frozen bread — is expanding too.
Patrick Duquennoy, director of NewCold France, tied the investment directly to that customer concentration, according to Radiofrance. “The extension was necessary because of the growth of Ysco, the ice cream maker — we had to expand to store their production, which is always made in advance, because the ice cream season is quite violent and quite fast,” he told Radio France.
Forty thousand pallets at minus 23 degrees
The scale of the structure is the story’s hardest numbers. Six thousand square meters of footprint. Thirty-two meters of height. Capacity for 40,000 pallets. Interior temperature held at minus 23 degrees Celsius, Radio France reported — conditions that require 30 new hires to work under adapted safety protocols.
Duquennoy framed the demand case beyond a single client. “Beyond the need from Ysco, the local market has demand. Many companies do frozen products — we can store prepared meals, fish, shrimp, bread, since Bridor has just built a plant in Falaise. We already work with them at our other site near Rennes,” he told Radio France. “So as soon as it’s frozen food, it can come to us.”
That Bridor detail matters for capacity planning across lower Normandy. The frozen bakery company opened a production plant in Falaise, and NewCold already counts it as a customer at a separate site near Rennes — meaning Argenta’s new volume is partly pre-committed before a single commercial pitch is made.
Three numbers that frame the investment
- €51 million — the cost of the new Argentan warehouse, the company’s second at the same industrial zone, 15 years after the first.
- 40,000 pallets — storage capacity, at 6,000 square meters and 32 meters of height, against demand the operator says is growing region-wide.
- One year — the time Duquennoy gave, per Radio France, before he expects the new site to reach saturation.
For a cold storage operator, a predicted twelve-month fill on a fresh €51 million asset is a statement about utilization economics, not caution. Warehousing margins live or die on occupancy rates; an operator forecasting saturation at opening is effectively betting the regional frozen food market has more volume than anyone has yet measured.
The local jobs arithmetic
Emmanuel Flouvat, the mayor of Argentan, put the employment scale-up in the context of his town’s labor priorities. Fifteen years ago, the first NewCold building set the template; the new one repeats it almost exactly.
“Structures like this, with 30 employees, are well sized for our territory,” Flouvat told Radio France, according to the report. That figure — 30 jobs for a 40,000-pallet automated-class facility — is the practical detail for a town weighing industrial recruitment against its workforce reality.
A Normandy freezer signals economic demand
Strip away the inauguration ribbon and this is a capacity investment responding to measurable demand: an ice cream producer scaling output, a frozen bakery opening a plant nearby, and a storage provider willing to double its footprint on the same industrial zone without relocating.
The concentration also says something about supply chains in the frozen food segment. Production built ahead of short seasonal windows — ice cream being the sharpest case, as Duquennoy described it — requires cold storage capacity to be contracted and in place before volumes arrive. When that capacity sits within kilometers of production, transport risk and energy costs both compress.
The counterweight is the timeline Duquennoy himself set. If the new site is saturated within a year, the question for NewCold and for Ysco becomes where the next 40,000 pallets of Normandy capacity come from — and whether a third building on the Putanges zone, or capacity elsewhere, follows the same math.
The Argentan site is a small piece of a much larger operation. NewCold, which launched its operations in 2012 with frozen potato producer Lamb Weston as its very first customer, is led by founder and CEO Bram Hage and today runs 22 warehouses across three continents, with a combined capacity of more than 1.7 million pallet positions and a workforce of 2,700 people.
Its largest European facility built in a single phase opened at Dinteloord in the Netherlands in April 2025 — a 40-meter-tall, grid-independent warehouse of 134,000 pallet positions and the company’s first greenfield project in its home country.
The facility’s operational numbers are confirmed; its economics rest on the operator’s own utilization forecast. NewCold’s director, for one, voiced no doubt: “He is therefore convinced by the profitability of the investment,” Radio France reported of Duquennoy, who anticipates saturation of the new site within a year.