San Francisco’s Board of Supervisors votes Tuesday on extending a citywide moratorium on new data centers by 10 months and 15 days, after a Planning Department report found the city’s power grid is nearing its 1,000-megawatt transmission limit — capacity city leaders may need for housing and electrification instead.
The vote lands at a moment when the math has stopped working. Peak demand into the city hit 900 megawatts in 2019, fell to roughly 800 megawatts by 2025 as offices emptied and population dipped, and is now climbing again by up to 20 megawatts a year, according to figures from PG&E cited by The San Francisco Standard.
Against a hard ceiling of about 1,000 megawatts, the margin is thin — and a single large data center would eat most of it.
The San Francisco Standard reported that the extension, File No. 261175, is an urgency ordinance from Supervisor Shamann Walton, co-sponsored by Supervisors Jackie Fielder, Chyanne Chen and Connie Chan. Because it runs under Section 65858 of the state Government Code, it needs nine of the board’s 11 votes. The original 45-day pause, Ordinance 215-26, expires at the end of November.
Here is the arithmetic the supervisors will weigh. The Planning Department’s Nov. 10 report, prepared at Mayor Daniel Lurie’s request, estimates that homes in the city use roughly 1 to 1.5 megawatts per 1,000 units. A 50-megawatt data center would draw as much power as more than 25,000 new homes; a hyperscale facility of 100 megawatts or more would match 50,000 or more.
Power Shortage Stalls Data Centers
- San Francisco’s grid ceiling is about 1,000 megawatts; peak demand was 900 megawatts in 2019 and is rising by at least 20 megawatts annually.
- A 50 MW data center consumes the power of 25,000+ new homes, making data centers and housing direct competitors for the same electrons.
- The city has no pending stand-alone data center applications; the vote decides whether to keep it that way for most of next year.
City Relies on Imported Power
Because it needs approval from nine of the board’s 11 members, the extension requires broad support from the supervisors. Its last two fossil-fuel plants, at Hunters Point and Potrero, were decommissioned — the last in 2011. Nearly all electricity arrives through a handful of connections, including the Transbay Cable, completed in 2010, which carries 400 of the city’s roughly 1,000 megawatts of peak transmission capacity.
The Planning Department’s warning is blunt. “Concern exists that construction of one or more large data centers in the nearer term could crowd-out available capacity needed for development of new housing and commercial space and for efforts to advance electrification before additional transmission capacity comes online,” the report says.
That crowding-out risk is where the market story lives. Oakland’s City Council voted last week to extend its own moratorium until October 2027, buying time to study grid, water and air-quality impacts — a precedent the San Francisco Standard notes directly.
Transmission Capacity History
The trajectory matters more than any single figure. Peak transmission into the city last touched 900 megawatts in 2019. Pandemic-driven population loss and office vacancies pulled it down to about 800 megawatts by 2025. The rebound since then reflects new construction, building electrification and electric vehicles — demand the city has deliberately encouraged.
| Measure | Figure | Source/Period |
|---|---|---|
| Max transmission capacity into city | ~1,000 MW | Planning Dept. report, 2026 |
| Transbay Cable share of capacity | 400 MW | Cable completed 2010 |
| Prior transmission peak | 900 MW | 2019 |
| Pandemic-rebound peak | 800 MW | 2025, per PG&E |
| Estimated annual demand growth | ~2% / up to 20 MW | PG&E and SFPUC estimate |
| 200 Paul Avenue facility scale | 493,000 sq ft / 38 MW | Planning Dept. estimate |
But the balance sheet tells a different story for the city’s housing goals. Every megawatt committed to a server hall is a megawatt unavailable for the electrification mandates and housing production San Francisco has legislated for. The report suggests officials could set a power-use threshold for all data centers citywide — effectively a cap — as one policy option.
Data Centers in Justice Zones
The geography adds a second layer to the decision. The Planning Department identified three stand-alone data centers: 200 Paul Avenue and 320-400 Paul Avenue in the Bayview, approved in 2013 and 2014 respectively, and 365 Main Street in the South of Market. All three sit inside designated environmental justice communities, and the Paul Avenue sites fall within the state’s AB 617 air-quality planning area for Bayview-Hunters Point.
Market intelligence firm Data Center Map identifies six data center locations citywide that rent out space or computing power, and the department concedes its three-facility list is not a complete inventory.
What the Report Leaves Unanswered
The Planning Department, by its own description, produced an initial assessment. It does not recommend for or against the extension. It flags gaps in its data and lists questions for further study: whether to cap data center power capacity, how to update the zoning code, and how to phase out diesel backup generators during outages.
The San Francisco Standard notes the city has no pending applications for a new stand-alone data center — which cuts both ways. The moratorium blocks nothing currently in the pipeline, but a year-long pause signals to developers and their hyperscaler customers that San Francisco is closed for that business until at least next fall.
For the broader economy, the signal compounds.
Supervisors Vote on Moratorium
Supervisors vote Tuesday on first reading of the extension ordinance. Nine votes would extend the pause for another 10 and 1/2 months; a failure lets the 45-day moratorium lapse at the end of November.
Either outcome sets the stage for the longer question the report leaves open: whether new transmission capacity arrives before demand does. As the Planning Department’s findings stand, the city’s power ceiling is fixed, its housing mandates are not negotiable, and the data center industry’s appetite is only growing. “Concern exists,” the report says — and the supervisors decide Tuesday what to do about it.