SUTTON, Mass. — The number that stopped this town cold: 900 megawatts.
That is roughly the electricity needed to power 450,000 homes, according to a town memorandum on the project, and it would be drawn by just ten buildings proposed for a rural parcel about 48 miles west of Boston. On Tuesday morning, residents fighting the $16 billion plan took their first formal step to stop it.
A petition bearing 346 signatures, gathered by resident Shawn Buzzell, was filed with the Sutton town clerk for certification, CBS News reported. It calls for a special town meeting where voters would rewrite the town’s zoning bylaws to ban data centers outright — not merely delay them.
“At that special town meeting we would be voting to amend the town’s zoning bylaws,” Buzzell told CBS News. Under his petition, a data center would be defined precisely, prohibited from “classifying themselves as anything else under acceptable use,” and barred from development in all zones in town.
The fight matters now because the timeline is tight. The planning board expects guidance from the state on data center regulations by the end of this year, and any zoning amendment requires a two-thirds majority at Town Meeting — likely in May 2027, according to remarks Town Manager Austin J. Cyganiewicz gave to The Boston Globe.
Ten buildings, 900 megawatts, one aquifer
The proposal, backed by The Kraft Group and Unified Global Packaging Group — both affiliated with New England Patriots owner Robert Kraft — would put ten data center buildings on land owned by Unified Packaging off Boston Road and Providence Road, near the Millbury border. The first two buildings, roughly 250,000 square feet each, would open in 2029, with two more added each year through 2033, boston.com and CBS News reported.

Robert Dufault went to town hall Tuesday to sign the petition, and raised the resource at the heart of residents’ fears. “We don’t have town water. So we have an aquifer under the town and the amount of water that a data center might use is phenomenal,” Dufault told CBS News. “I would hate to see Sutton sell its soul.”
At full build-out, the campus would rank among the largest data centers in the country, according to the town memorandum WBUR reviewed. Residents skeptical of the scale packed a Monday night planning board meeting — about 75 of them, some holding signs reading “NO DATA CENTERS.”
A Select Board meeting the week before was even tenser: boston.com reported that more than 100 residents jammed the room, and one man was removed by a police officer.
The tax math, and the hole it fills
The project’s appeal to town leaders is stark arithmetic. Sutton currently assesses all property at about $2.85 billion; the developer values just the first two buildings, servers included, at roughly $3.35 billion, Cyganiewicz told boston.com.
He estimated the first phase would generate about $10.4 million a year in property taxes starting in fiscal 2031, rising to about $27.8 million a year by 2035 — and cut the tax bill on the average single-family home, assessed at $662,000, by roughly $2,300 in 2031.
| Figure | Amount | Source |
|---|---|---|
| Proposed project value | $16 billion | Town memorandum |
| Sutton’s total assessed property | about $2.85 billion | Cyganiewicz, via boston.com |
| Property tax revenue, fiscal 2031 | about $10.4 million | Cyganiewicz, via boston.com |
| Property tax revenue by 2035 | about $27.8 million | Cyganiewicz, via boston.com |
| Projected deficit by 2033 without new revenue | about $10 million | Cyganiewicz’s memo, via The Boston Globe |
The revenue pitch lands against a real fiscal squeeze. The Boston Globe reported that Sutton faces a deficit of about $350,000 in the fiscal year starting July, projected to grow to $2.5 million in the next budget cycle and about $10 million by 2033 — and Massachusetts municipalities must balance budgets by law.

Six speakers, zero in favor
At Tuesday’s Select Board meeting, six residents spoke during public comment, and all opposed the project, boston.com reported. Retired physician Roseanne Labarre called the health risks unacceptably high and demanded a moratorium.
“The risks are too great … I propose a moratorium on data center development in Sutton before we cause irreparable environmental and personal harm.”
Labarre said at the meeting, according to boston.com.
Former Select Board member Mario Giamei urged the board to reflect public sentiment, framing the opposition as overwhelming: “I think you’re going to see that this is a 70 or 80 percent ‘no’ issue, and at that point, you should do the will of the people of this town,” he said, per boston.com.
And 45-year resident Sarah Osterman Stone asked board members to “keep the residents of this town centered in this discussion.”
Moratorium pauses development
A moratorium, if pursued, would freeze the project for a year, blocking any development permissions while a data center bylaw is drafted, CBS News reported. The town’s own statement last Friday stressed that nothing has been decided: applications have not been filed, and “important details on power, water, equipment and site impacts are still to come,” the town memo reads, as WBUR reported.

“Considering an opportunity is not the same as supporting it,” the town statement said, according to The Boston Globe.
The Kraft Group, for its part, issued a statement Thursday night billing the campus as “an opportunity to bring meaningful long-term economic investment to Sutton” and pledging that “this project will only move forward if the community and the Town of Sutton want it,” The Boston Globe reported. WBUR said it received no response from the company in time for publication.
One thing worth watching: how the state’s newest rule intersects with this fight. Gov. Maura Healey signed an executive order in September requiring data center projects to win local approval before obtaining state permits, and to develop their own energy resources or create a “Ratepayer Protection Fund” if they cannot, WBUR reported — a threshold Buzzell’s petition aims to reach first.
“I wouldn’t say that the entire town is blanket opposed to data centers. The beautiful thing about this amendment is it allows us to still go back to the table, we can amend, we can define what we do want in the community, instead of being told what we should have.”
The town has posted project information at its Proposed Data Center Project page, and officials are scouting larger venues for meetings that keep outgrowing their rooms.