Nine proposed data centres could add 40 million tonnes of climate pollution a year by 2035 if they run without new renewables — almost as much as the Loy Yang A, Eraring and Bayswater coal stations combined, a report released on Thursday warns.
The analysis, Pollution Pipeline: Australia’s Dirtiest Data Centres, was released by the Climate Council and the Carbon Zero Initiative as the federal government weighs national regulations.
Draft legislation is expected before the end of the year. The report lands amid a community backlash that has, in five months, gone from failed council motions to unanimous moratorium calls and scrapped projects.
The nine proposals — four in NSW, three in Victoria, and one each in Queensland and the Northern Territory — would consume more than 50 terawatt hours a year, the report found. That is over two-thirds of the power Australian households use. Seven would connect to the grid; two would use dedicated gas-fired power stations.
“Gas corporations looking to justify burning more gas have spotted data centres and are circling like seagulls around a bag of hot chips,” said Climate Council chief executive Amanda McKenzie. “If we let them lock in giant gas power stations now that will pollute for decades, we'll be paying the price.”
Power Bills Rise 20 per Cent
Without new renewables and storage, data centre demand could push wholesale power prices up 20 per cent across the main grid by 2035, the report estimates. The rise would be even larger in NSW and Victoria.
The report also flags a second cost: data centre investment is fuelling above-target inflation of 4.3 per cent. Reserve Bank Governor Michele Bullock has said that inflation is adding pressure to an already constrained economy.
Independent Senator David Pocock, who has proposed a 5 per cent tax on large AI data centres, called the threatened emissions “totally irresponsible”. “We're talking about huge emissions at a time where the world desperately needs to reduce our emissions,” he said. He added that he was concerned the government was so focused on attracting data centres that climate impacts were going undiscussed.
University of Sydney Institute for Sustainable Futures research director Chris Briggs told AAP the boom could help or hurt the clean energy transition. “We could either see a reversal of the cleaning of our power system that's been under way or, conversely, if it's done right, data centres could actually help accelerate it,” he said, while acknowledging the worst-case scenario was “certainly a possibility”.
Industry Pushes Back
Data Centres Australia, the peak body for developers, said the report rests on “speculative” demand. Chief executive Belinda Dennett said operational data centres already offset 70 per cent of their energy use with renewable energy. Companies were stepping up consultation through information sessions, door knocking and hotlines, she said.
The industry’s own figures are substantial. A Data Centres Australia report found the opportunities to 2030 include $19.8 billion in construction and 18,930 construction jobs, plus $5.6 billion in ongoing operations and 23,040 ongoing jobs.
Australia is the world’s second-largest data centre investment destination after the US. Investment is estimated to top $155 billion in the coming decade, according to Westpac Economics.
“Data centres don't have to drive up power prices and pollution,” said Carbon Zero Initiative co-founder Alexander Hoysted. “Australia has one chance to lock in strong guardrails that work to our nation's advantage, not just throw down the welcome mat for big tech to come here on their own terms.”
Five Months Change the Politics
When Wingecarribee councillor Heather Champion moved against a gas plant powering a southern highlands data centre in March, the motion failed. Five months later, a moratorium motion passed unanimously. “I think the council's change in perspective is a direct result of the change in sentiment in the community,” Champion told Guardian Australia.
In September, Goodman Group walked away from an $800 million, 24/7 data centre at Lane Cove. Resident protests and concerns from Sydney Water and Ausgrid about strained infrastructure and fire and electrocution risks drove the exit.
NextDC’s M3 expansion in West Footscray has been stalled after power provider Jemena delayed installation of power poles. NextDC’s share price fell almost 40 per cent as a result. A petition against the Western Downs Digital Park near Dalby has drawn more than 24,000 signatures.
The consequences reach the building trade: contractor Kapitol Group, a major NextDC builder, is looking for other work and expanding into Queensland as clients put projects on hold, the Australian Financial Review reported. Campaigners are now coordinating nationally through WhatsApp and community wikis, borrowing tactics from US groups that made data centres a decisive issue in the midterm elections.
Report Demands New Renewables
The report’s central ask covers every facility over 30 megawatts starting operation after March 23, 2026. Each would have to match its demand with new renewables and storage. Gas would be ruled out as a primary power source, and fresh water would be banned for cooling in water-stressed regions.
McKenzie put the choice simply: “It's simple: If you want to plug into our grid, bring your own renewable power: solar, wind and batteries.”
The Climate Council, which has published more than 100 research reports to date, was formed in 2013 by former members of the Climate Commission after the Abbott government disbanded that body. Within a day of the announcement, donations from 7,200 members of the public had raised $218,000, and by the end of the first week more than 20,000 people had given close to $1 million.
The Council, now with 11 Councillors spanning climate science, bushfires, health and energy, remains funded mostly by donors — 89 per cent of its funding — and was a prominent commentator linking the Black Summer bushfires to climate change.
Draft national legislation is expected before the end of the year — the window in which both sides of this fight say the rules will be set.