The Senate voted 73-25 on Monday to advance debate on the Bipartisan American Affordability and Jobs Act, a sweeping energy permitting bill that would for the first time require large data centers to pay the full grid costs they create.
The 494-page bill would speed federal environmental reviews for power plants, transmission lines and gas pipelines. “The day of data center freeloading ends when this bill passes,” said Sen. Sheldon Whitehouse, D-R.I., a co-author of the bill.
A novel provision directs the Federal Energy Regulatory Commission to write rules within 90 days charging data centers both for grid upgrades needed to serve them and for using the existing network. That would overturn regulatory principles dating back to 1994 that forbid utilities from charging customers twice for the same grid capacity — in effect, large data centers could be billed roughly double what they pay now.
“Democrats ran and won on affordability and data center accountability, and BAAJA will allow us to start delivering immediately on both of those election promises,” Sen. Sheldon Whitehouse of Rhode Island, the top Democrat on the Senate's environment committee and one of the bill's authors, told Reuters.

Supporters call it Congress' first real answer to the public anger over data centers and rising electricity bills that powered Democrats to a landslide in this month's midterms. In those midterms, voters approved at least 40 local ballot initiatives restricting the facilities.
What the bill would change
Historically, utilities have spread the cost of grid upgrades across all their customers. The bill would upend that decades-old arrangement. “Data centers now have to pay for the extra costs that they bring to the grid when they come online. They do not get to have all that extra cost dumped out onto the utility's rate base and picked up by all of the other ratepayers,” said Sen. Sheldon Whitehouse, D-R.I., a co-author of the bill.
A report from the consulting firm Grid Strategies estimates the federal grid rules alone could cost data centers an extra $35 billion over the next 10 years — money that could offset transmission costs for other customers. If tech companies took full advantage of the bill’s other provisions, they could raise an additional $136 billion, the report found.
Other provisions would let state regulators charge data centers extra for the power plants they need and credit household bills with the money. The bill would also require the federal government to track data center energy use for the first time. It would scale back laws like the National Environmental Policy Act to speed construction, and could hinder future presidents from imposing a moratorium on data centers on public lands.
The politics are thornier than the vote count suggests
Some Democrats who campaigned on reining in data centers worry the provisions could encourage even more construction. Senator Ron Wyden, an Oregon Democrat, said Friday that his party should use its post-election leverage to negotiate a different approach on permitting. House Democratic Leader Hakeem Jeffries, expected to become speaker next year, told Politico the bill falls short on environmental protections.
Environmental groups including the Sierra Club said a Saturday package of amendments would not resolve their objections.
Data Centers Could Use 426 Terawatt-Hours by 2030
The stakes are large. U.S. data centers consumed about 183 terawatt-hours of electricity in 2024, according to figures cited by the Pew Research Center, and that could reach 426 terawatt-hours by 2030. A Pew survey published Wednesday found 60% of Americans would be uncomfortable with a new data center in their neighborhood.

Rhodium Group found the bill’s transmission and permitting reforms could cut greenhouse-gas emissions tied to data center operations by 31% to 90%, depending on the power mix, by letting demand be served through a cleaner grid rather than dedicated gas plants, Reuters reported.
Bill Stops at Texas’ Main Grid and Local Permits
Texas hosts many data centers, but FERC lacks authority over the state’s main grid, ERCOT, and the bill’s effect there is unclear. State utility commissions would also have to work out how to assign transmission costs.
And one big unknown, the New York Times reports: higher grid charges might push tech companies off the grid entirely. Developers are already planning dozens of off-grid data centers running on inefficient gas turbines or repurposed jet engines.
The bill would not affect many state and local permits, and communities could still impose their own restrictions. The Senate takes up amendments as debate continues this week, with Democrats set to control both houses of Congress in 2026 and promising a wave of further bills targeting AI and data center development.
Earlier coverage: Why Many Announced AI Data Center Projects May Never Be Built